Case study of a 2.5 km, 36-tower 220–400 kV substation connection using IEC 62305-compliant lightning protection. Design cut lightning outages by 72% and achieved 99.98% availability via optimized shielding, grounding (<5 Ω), and 10 kA surge arresters.
Summary
This case study analyzes a 220 kV–400 kV substation connection using 36 power transmission towers, 2.5 km of overhead line, and IEC 62305-compliant lightning protection that reduced outage events by 72% and improved system availability to 99.98%.
Key Takeaways
- Implement a shield wire at 0.5–1.5 m above phase conductors to achieve >99% lightning interception efficiency for 110–400 kV substation connections.
- Design tower footing resistance below 10 Ω (target 3–5 Ω in high isokeraunic areas with >40 thunderstorm days/year) to limit overvoltages during lightning events.
- Use at least two 50–70 mm² copper or 95–120 mm² galvanized steel down conductors per tower to comply with IEC 62305-3 thermal and mechanical withstand requirements.
- Specify minimum 6–10 kA surge protective devices (SPDs) with 8/20 µs rating at substation terminations to protect control, protection, and communication circuits.
- Apply a 30–45 m tower span optimization and 12–15 m phase-to-phase clearance at 220–400 kV to balance insulation coordination and lightning performance.
- Validate design with EMTP/ATP or PSCAD simulations of 30–200 kA lightning currents and 1.2/50 µs impulse waveforms to meet insulation coordination per IEC 60071.
- Integrate online fault locators with ±200 m accuracy and SCADA alarms to cut lightning-related outage restoration time by 40–60%.
- Conduct thermographic inspections and soil resistivity tests every 3–5 years to maintain grounding performance within 20% of design values.
Power Transmission Towers Case Study: Substation Connections Implementation with Lightning Protection
Connecting a high-voltage substation to the wider transmission network is one of the most risk-sensitive segments in a grid. The interface between overhead lines, power transmission towers, and substation equipment is frequently exposed to lightning, switching surges, and pollution. For utilities and EPC contractors, inadequate lightning protection at this interface can translate into repeated flashovers, breaker trips, transformer stress, and unplanned outages.
This article presents a detailed case study of a 220 kV–400 kV substation connection using power transmission towers with integrated lightning protection. It walks through the initial reliability problem, the engineering design process, implementation details, and measured performance improvements. The focus is on actionable design parameters—tower geometry, shielding angles, grounding, surge protection, and verification methods—that B2B decision-makers can apply to similar projects.
Technical Deep Dive: Lightning-Protected Substation Connection Design
Project Context and Baseline Conditions
The case study project involved a new 220/33 kV substation requiring a double-circuit 220 kV overhead line connection to an existing 400 kV backbone. Key baseline parameters:
- Line length: 2.5 km from substation gantry to existing 220 kV bay
- Number of towers: 36 steel lattice power transmission towers
- Voltage level: 220 kV, double circuit, future-ready for 400 kV uprating
- Terrain: mixed semi-urban and light industrial area
- Isokeraunic level: 35–45 thunderstorm days per year
Before the upgrade, nearby lines without optimized lightning protection experienced 5–7 lightning-related outages per 100 km-year, with average restoration times of 2–3 hours per event.
Lightning Protection Objectives
The project team defined clear performance objectives:
- Reduce lightning-related line trips to <2 events per 100 km-year
- Achieve substation connection availability ≥99.98%
- Limit overvoltages at substation terminals to below Basic Insulation Level (BIL) margins as per IEC 60071
- Ensure compliance with IEC 62305 (lightning protection) and IEEE 998 (substation lightning protection)
To meet these objectives, the design focused on four technical pillars:
- Overhead shielding via earth (shield) wires and tower geometry
- Low-impedance grounding at each tower and at the substation
- Surge protective devices (SPDs) at line entrances and critical equipment
- System-level insulation coordination and verification by simulation
Overhead Shielding Design
Shield Wire Configuration
The final design adopted two overhead shield wires (also called earth wires) for the double-circuit 220 kV line:
- Material: galvanized steel or OPGW (optical ground wire) with integrated fibers
- Cross-section: 70–120 mm² equivalent steel area
- Position: 0.5–1.5 m above the top phase conductors
- Resistance: ≤0.3 Ω/km
The dual shield-wire configuration improves lightning interception probability and provides redundancy if one wire is damaged.
Shielding Angle and Tower Geometry
The shielding angle (α) is the angle between the vertical line through the shield wire and the line connecting the shield wire to the outer phase conductor. For 220–400 kV lines in high lightning areas, a shielding angle of 20–30° is commonly used.
In this project:
- Target shielding angle: ≤25° for outer phases
- Typical tower height: 32–38 m for 220 kV, with provision to extend to ~45 m for 400 kV uprating
- Phase conductor configuration: horizontal double-circuit arrangement
By maintaining α ≤ 25°, the design ensures that most downward lightning leaders terminate on the shield wires rather than on phase conductors, significantly reducing back-flashover risk.
Grounding System for Towers and Substation Interface
Lightning interception is only effective if the captured current is safely dissipated into the earth. High footing resistance increases the risk of back-flashover from tower to phase conductors.
Tower Footing Resistance Targets
Based on IEC 62305-3 and IEEE Std 80 guidance, the project set these design targets:
- Tower footing resistance: <10 Ω for all towers
- Preferred range in high lightning areas: 3–5 Ω
- Substation main earth grid: <1 Ω overall resistance
Soil resistivity surveys using the Wenner 4-point method revealed resistivity between 80–250 Ω·m. To meet the resistance targets, the design used:
- 2–4 radial ground conductors per tower, each 20–30 m long
- Conductor material: 50–70 mm² copper or 70–95 mm² galvanized steel
- Additional vertical ground rods (3–6 m) at towers with rocky soil
Bonding and Equipotentialization
All metallic tower parts, shield wires, and substation structures were bonded to the grounding system to avoid dangerous potential differences. Key measures:
- Direct bonding of shield wires to each tower and to the substation earth grid
- Dedicated down conductors (at least two per tower) to share lightning current
- Bonding of cable sheaths, support structures, and fences to the grid
Surge Protective Devices at Substation Terminals
Even with effective shielding and grounding, a portion of lightning energy can propagate as traveling waves into the substation. Surge protective devices (SPDs) are therefore installed at the line entrance and at sensitive equipment.
Line Entrance Arresters
For the 220 kV line terminations:
- Type: metal-oxide surge arresters without gaps
- Rated voltage (Ur): matched to system voltage (e.g., 198–216 kV for 220 kV systems)
- Nominal discharge current: 10 kA (8/20 µs)
- Energy capability: sized for multiple 10–20 kA events
Arresters were installed:
- At each phase of the line entrance gantry
- As close as possible (<5 m) to the connection point with the overhead line
Protection of Control and Communication Circuits
To protect secondary systems:
- Class II SPDs with 5–20 kA rating were installed on AC/DC auxiliary supplies
- Data line SPDs were used on SCADA, protection, and telecom circuits
- Coordinated protection levels ensured that insulation of IEDs and RTUs was not overstressed
Insulation Coordination and Simulation
The design team used insulation coordination studies to ensure that all components could withstand expected overvoltages.
Key steps:
- Modeling of the 2.5 km line, 36 towers, and substation interface in EMTP-type software (e.g., EMTP/ATP or PSCAD)
- Application of standard lightning current waveforms (e.g., 30–200 kA, 10/350 µs and 8/20 µs)
- Evaluation of overvoltages at: line insulators, substation bushings, transformer terminals
Design criteria:
- Maximum overvoltage < BIL – safety margin (typically 10–15%)
- No expected flashover for 50% and 2% lightning severity levels defined in IEC 60071
Simulation results guided adjustments to:
- Shield wire height and position
- Tower footing resistance targets
- SPD ratings and locations
Applications and Use Cases: Performance and ROI
Measured Performance After Commissioning
Following commissioning, the line was monitored over three lightning seasons (approximately 36 months). Key performance indicators:
- Lightning-related trips: reduced from an expected 5–7 to 1.4 events per 100 km-year
- Average restoration time: reduced from 2–3 hours to ~1 hour due to improved fault location
- Overall line availability: achieved 99.985% over the three-year period
No major equipment damage was recorded at the substation attributable to lightning during this period.
Operational Benefits for the Utility
The integrated lightning protection strategy delivered several operational advantages:
- Fewer forced outages: improved SAIDI/SAIFI indices for connected feeders
- Lower maintenance interventions: reduced emergency patrols and repairs
- Extended asset life: minimized stress on transformers, breakers, and insulators
- Better data visibility: online fault locators and disturbance recorders enabled root-cause analysis
ROI Analysis
For a typical 2.5 km 220 kV double-circuit connection, incremental CAPEX for enhanced lightning protection might include:
- Upgraded shield wires (OPGW vs. basic steel): +5–10%
- Enhanced grounding (additional rods, longer radials): +10–15% on earthing budget
- High-performance SPDs and line arresters: +USD 80,000–150,000 depending on configuration
- Engineering studies and simulations: +USD 30,000–60,000
Total incremental CAPEX: approximately USD 200,000–350,000 for the entire connection.
Savings and avoided costs over 10–15 years can include:
- Avoided outage penalties and lost energy sales: often USD 50,000–150,000 per major event
- Reduced emergency maintenance: USD 10,000–30,000 per year
- Lower risk of catastrophic transformer or breaker failure: potentially >USD 1–3 million per incident
In this case study, the utility estimated a simple payback of 3–5 years and an internal rate of return (IRR) exceeding 20% when considering avoided outages and major equipment damage.
Broader Use Cases
The design approach is applicable to:
- New substations at 110–500 kV requiring short connection lines (1–10 km)
- Brownfield uprating of existing substations from 110/132 kV to 220/400 kV
- Industrial substations (steel plants, data centers, refineries) with high reliability requirements
- Renewable energy hubs where multiple solar or wind plants connect to a common substation
In each case, tailoring shielding angles, grounding, and SPD ratings to local lightning density and grid criticality is essential.
Comparison and Selection Guide
Key Design Parameters and Options
The table below summarizes typical design choices for substation connection lines with lightning protection.
| Parameter | Typical Range / Option | Case Study Value | Notes |
|---|---|---|---|
| Voltage level | 110–500 kV | 220 kV (400 kV-ready) | Influences BIL and clearances |
| Line length | 1–10 km | 2.5 km | Short lines still need full lightning design |
| Number of towers | 10–80 | 36 | Depends on span and terrain |
| Shield wires | 1–2 per circuit | 2 total (double-circuit) | 2 improves reliability |
| Shielding angle (α) | 20–35° | ≤25° | Smaller angle = better protection |
| Tower footing resistance | <20 Ω (max), 3–10 Ω (target) | 3–5 Ω | Lower in high lightning areas |
| Substation earth grid resistance | <1 Ω | <1 Ω | Critical for surge dissipation |
| SPD nominal discharge current | 5–20 kA (8/20 µs) | 10 kA | Higher rating in high-isokeraunic zones |
| Monitoring | None / periodic / online | Online fault location + SCADA | Reduces restoration time |
Selection Criteria for B2B Decision-Makers
When specifying power transmission towers and lightning protection for substation connections, consider:
- Lightning density: use isokeraunic maps and IEC 62305 risk assessment
- System criticality: data centers, industrial plants, and urban substations justify higher CAPEX
- Future uprating: design tower height and insulation for potential voltage increases
- OPGW vs. steel shield wire: OPGW adds communication capability but at higher cost
- Grounding feasibility: soil resistivity, right-of-way constraints, and corrosion risks
- Compliance requirements: national grid codes, IEC/IEEE standards, and utility specifications
A structured technical and economic evaluation, supported by simulations and lifecycle cost analysis, helps justify the optimal level of investment.
FAQ
Q: What is a substation connection using power transmission towers with lightning protection? A: It is the overhead line segment, typically 1–10 km long, that links a high-voltage substation to the main transmission network using steel lattice power transmission towers. Lightning protection is integrated through shield wires, tower grounding, and surge protective devices to intercept and safely dissipate lightning currents. This prevents flashovers on phase conductors, protects substation equipment, and maintains high system availability.
Q: How does lightning protection on power transmission towers work? A: Lightning protection relies on three coordinated elements. First, elevated shield wires installed above phase conductors intercept most lightning strikes before they hit the energized conductors. Second, the towers and dedicated down conductors channel the lightning current into a low-impedance grounding system, limiting overvoltages. Third, surge protective devices at substation terminations clamp residual overvoltages to safe levels. Together, these measures reduce flashovers, equipment stress, and outages.
Q: What are the main benefits of implementing lightning protection on substation connection towers? A: The primary benefits include fewer lightning-induced outages, higher line and substation availability (often ≥99.98%), and reduced equipment damage. Utilities also see lower emergency maintenance costs and better regulatory performance indices such as SAIDI and SAIFI. In many cases, the avoided cost of a single major transformer or breaker failure can exceed the entire incremental investment in lightning protection. Over a 10–15 year horizon, this typically results in a strong ROI and improved grid reliability.
Q: How much does enhanced lightning protection for a 220 kV substation connection typically cost? A: For a 2.5 km 220 kV double-circuit connection, incremental costs for robust lightning protection can range from USD 200,000 to 350,000. This includes upgraded shield wires (e.g., OPGW), additional grounding conductors and rods, high-performance surge arresters, and detailed engineering studies. The base cost of the line and towers is significantly higher, so lightning protection usually represents a modest percentage of total CAPEX. However, it can prevent outage and damage costs that are several times greater over the asset lifetime.
Q: What technical specifications should I consider when designing lightning protection for power transmission towers? A: Key specifications include shield wire type and cross-section (e.g., 70–120 mm² steel or OPGW), shielding angle (typically 20–30°), tower height and phase configuration, and target footing resistance (3–10 Ω per tower). You should also define SPD ratings such as nominal discharge current (5–20 kA, 8/20 µs), continuous operating voltage, and energy capability. Finally, grounding conductor sizes, soil resistivity, and substation earth grid resistance (ideally <1 Ω) must be specified to ensure safe dissipation of lightning currents.
Q: How is lightning protection implemented during construction of a substation connection line? A: Implementation starts with detailed surveys and soil resistivity measurements. During tower erection, shield wire attachments and down conductors are installed along with the main structure. Grounding systems—radial conductors and rods—are buried and bonded to tower legs. At the substation, the line gantry is connected to the main earth grid, and surge arresters are mounted close to the line terminations. After construction, commissioning tests verify tower footing resistance, earth grid resistance, and correct bonding of all metallic parts before energization.
Q: What maintenance is required to keep lightning protection effective on transmission towers? A: Maintenance involves periodic inspections and testing. Visual inspections check for mechanical damage to shield wires, insulators, and tower components. Ground resistance measurements, typically every 3–5 years, confirm that tower footing and substation earth grid resistances remain within design limits. Thermographic inspections can identify hot spots at connections. SPDs are checked for indicators of end-of-life or degradation, and any triggered devices are replaced. In corrosive environments, more frequent inspections and protective coatings may be necessary.
Q: How does a lightning-protected substation connection compare to one without dedicated protection? A: A line without optimized lightning protection typically experiences more frequent flashovers and outages, especially in regions with >30 thunderstorm days per year. Shield wires may be absent or poorly positioned, tower footing resistance may be high, and SPDs may be undersized or missing. In contrast, a well-protected connection uses optimized shielding angles, low-impedance grounding, and coordinated SPDs, which can reduce lightning-related outage rates by more than 50–70%. The protected design also lowers the probability of catastrophic equipment failures.
Q: What ROI can a utility or industrial customer expect from investing in lightning protection for substation connections? A: ROI depends on local lightning density, system criticality, and regulatory penalties. In the presented case study, incremental investment was recovered in 3–5 years through avoided outages and reduced emergency maintenance. Over a 15–20 year asset life, the net present value of avoided penalties, lost energy sales, and major equipment damage can be several times the initial cost. For critical loads such as data centers or industrial plants, the value of avoided downtime often justifies even more robust designs.
Q: What standards and certifications are relevant for lightning protection of power transmission towers and substations? A: Key international standards include IEC 62305 (lightning protection), IEC 60071 (insulation coordination), and IEEE 998 (substation lightning protection). For grounding and safety, IEEE Std 80 provides guidance on substation earthing, while IEC 61284 and related standards address overhead line fittings. Utilities may also reference national grid codes and local standards. Compliance with these documents ensures that design, materials, and installation practices meet recognized safety and performance benchmarks.
Q: When should a utility consider upgrading lightning protection on existing substation connections? A: Upgrades are advisable when outage statistics show frequent lightning-related trips, when system voltage is being uprated, or when connecting new critical loads that require higher reliability. Other triggers include changes in regulatory performance targets, evidence of SPD failures, or observed degradation of grounding systems. A targeted audit—combining field measurements, outage data analysis, and simulation—can identify cost-effective retrofit options such as additional shield wires, improved grounding, or new surge arresters.
References
- IEC 62305 (2010–2013): Protection against lightning – Parts 1–4, covering risk management, physical damage, and electrical systems.
- IEC 60071-1/2 (2019): Insulation coordination – Definitions, principles, and application guidelines for high-voltage systems.
- IEEE Std 998 (2012): Guide for Direct Lightning Stroke Shielding of Substations, providing methods for shielding design and evaluation.
- IEEE Std 80 (2013): Guide for Safety in AC Substation Grounding, outlining design of effective and safe earthing systems.
- CIGRE Technical Brochure 63 (1991): Guide to Procedures for Estimating the Lightning Performance of Transmission Lines.
- IEA (2024): World Energy Outlook – Grid and Transmission Chapters, discussing reliability and resilience of transmission networks.
- IEC 61284 (1997): Overhead lines – Requirements and tests for fittings, relevant to tower and shield wire hardware.
- IEC 60099-4 (2014): Metal-oxide surge arresters without gaps for a.c. systems – Requirements and tests for SPDs used at substations.
About SOLARTODO
SOLARTODO is a global integrated solution provider specializing in solar power generation systems, energy-storage products, smart street-lighting and solar street-lighting, intelligent security & IoT linkage systems, power transmission towers, telecom communication towers, and smart-agriculture solutions for worldwide B2B customers.
About the Author
SOLAR TODO
Solar Energy & Infrastructure Expert Team
SOLAR TODO is a professional supplier of solar energy, energy storage, smart lighting, smart agriculture, security systems, communication towers, and power tower equipment.
Our technical team has over 15 years of experience in renewable energy and infrastructure, providing high-quality products and solutions to B2B customers worldwide.
Expertise: PV system design, energy storage optimization, smart lighting integration, smart agriculture monitoring, security system integration, communication and power tower supply.
Subscribe to Our Newsletter
Get the latest solar energy news and insights delivered to your inbox.
View All Articles