SOLARTODO / Field wiring
11 main exits
Index
←
01 · OPENINGS · Center pivot field wiring
02 · TOWER-OPENINGS · End-tower cabinet openings
03 · CONTENTS · Field cables and roof feeders
04 · INDEX-BOX · Separate-box cable variants
05 · INDEX-MAIN · Inside the main cabinet
06 · INDEX-TOWER · Inside the end tower and field records
07 · METHOD · Prepare, identify and prove the cable
08 · INTERFACES · Identify the feedback interface
09 · M01 · Main cabinet supply and protective earth
10 · M02 · Start, stop and returned run status
11 · M03 · Forward command and feedback
12 · M04 · Reverse command and feedback
13 · M05 · Original cabinet fault feedback
14 · M06 · Local mode and takeover feedback
15 · M07 · Main sprinkler supply and feedback
16 · M08 · Single end gun and feedback
17 · M09 · Cable monitor data pair
18 · M10 · Reserved standard travel-speed cable
19 · M11 · Optional agricultural sensor cable
20 · E01 · End-tower supply and protective earth
21 · E02 · Four end-tower fault inputs
22 · E02-S · Tower faults · single external cable
23 · E02-M · Tower faults · machine-side cable
24 · E02-C · Tower faults · controller-side cable
25 · AR1 · Cellular gateway antenna feeder
26 · AR2 · Pivot-center GPS A feeder
27 · AR3 · Main local-radio antenna feeder
28 · BR1 · Tower local-radio antenna feeder
29 · BR2 · End-tower GPS B antenna feeder
30 · M02-C · Run / stop · controller side cable
31 · M02-M · Run / stop · machine side cable
32 · M03-C · Forward · controller side cable
33 · M03-M · Forward · machine side cable
34 · M04-C · Reverse · controller side cable
35 · M04-M · Reverse · machine side cable
36 · M05-C · Panel fault · controller side cable
37 · M05-M · Panel fault · machine side cable
38 · M06-C · Local mode · controller side cable
39 · M06-M · Local mode · machine side cable
40 · M07-C · Span spray · controller side cable
41 · M07-M · Span spray · machine side cable
42 · M08-C · End gun · controller side cable
43 · M08-M · End gun · machine side cable
44 · MI01 · Main cabinet AC feed-through and earth
45 · MI02 · 24 V DC supply distribution
46 · MI03 · Main controller 24 V branch
47 · MI04A · Cellular gateway 24 V branch
48 · MI04B · Main local radio 24 V branch
49 · MI05 · Controller to gateway Ethernet
50 · MI06 · Controller to main radio RS-485
51 · MI07A · Run and direction command pigtails
52 · MI07B · End-gun and span-spray command pigtails
53 · MI08 · Feedback strip to controller inputs
54 · MI09A · Feedback returns to block 1
55 · MI09B · Feedback returns to block 2
56 · MI10A · DGND to return block 1
57 · MI10B · Return block 1 to return block 2
58 · MI11 · Isolated run and direction feedback
59 · MI12 · Isolated end-gun and panel fault feedback
60 · MI13 · Isolated local mode and span-spray feedback
61 · MI14A · Option cabinet · isolated measurement pair
62 · MI14B · Option cabinet · acquisition module power
63 · EI01 · End tower AC feed-through and earth
64 · EI02 · 12 V DC supply distribution
65 · EI03A · Tower local radio 12 V branch
66 · EI03B · GPS B receiver 12 V branch
67 · EI03C · Tower input collector 12 V branch
68 · EI04A · Collector input COM positive lead
69 · EI04B · 0 V feed to the tower return block
70 · EI05A · RS-485 · Tower local radio
71 · EI05B · RS-485 · GPS B receiver
72 · EI05C · RS-485 · Tower input collector
73 · EI06A · Fault feed-through signal pigtails
74 · EI06B · Fault feed-through return pigtails
75 · EI07 · Optional tower isolation contact pigtails
76 · COM-1 · Commission travel, stop and local control
77 · COM-2 · Commission water, data and fitted options
78 · RECORD · As-built cable and core record
79 · HANDOVER · Acceptance and handover
80 · EVIDENCE · What the project records establish
→
Enlarge
Open PDF ↗
Center pivot field wiring
Main cabinet / Eleven numbered bottom openings and three roof feeders. Select an outlet to open its wiring sheet.
SOLARTODO / FIELD WIRING & COMMISSIONING
Center pivot field wiring
Main cabinet / Eleven numbered bottom openings and three roof feeders. Select an outlet to open its wiring sheet.
Main cabinet opening map
Eleven individually numbered bottom openings and three separate top feeders. Each links to its own wiring plate.
MAIN CABINET · REFERENCE FRONT VIEW
11 bottom cable openings / 3 top antenna feed-throughs
MAIN RETROFIT CABINET
Front view with door open. Find the numbered cable gland before pulling the cable.
AC
Supply and PE
Incoming AC and 24 V distribution.
I/O
Controller
Commands and digital feedback.
TB
Terminal strips
Command, isolated return and bus groups.
RF
Gateway and radio
Cellular, fixed GPS A and the radio link.
BOTTOM GLAND ROW · MATCH THE NUMBER ON THE ACTUAL ENCLOSURE
M-AR1 4G LTE
Cellular coax
M-AR2 GPS A
Fixed center positioning coax
M-AR3 RADIO 2.4GHZ
Cabinet-to-tower radio coax
M01
AC supply and PE
M01 AC POWER IN 110VAC
3 × 1.5 mm² · confirm supply
→
M02
Start, stop and status
M02 RUN / STOP
4 × 0.75 mm² · control
→
M03
Forward and status
M03 FORWARD
4 × 0.75 mm² · control
→
M04
Reverse and status
M04 REVERSE
4 × 0.75 mm² · control
→
M05
Panel fault status
M05 PANEL FAULT
2 × 0.75 mm² · control
→
M06
Local-mode status
M06 LOCAL MODE
2 × 0.75 mm² · control
→
M07
Main water supply
M07 SPAN SPRAY
4 × 0.75 mm² · control
→
M08
Single end gun
M08 END GUN
4 × 0.75 mm² · control
→
M09
Optional cable monitor
M09 CABLE MONITOR
2 × 0.75 mm² · 120 Ω STP
→
M10
Reserved speed control
M10 SPEED CONTROL
4 × 1.0 mm² · control
→
M11
Optional sensor bus
M11 SENSORS
2 × 0.75 mm² · 120 Ω STP
→
Match the enclosure number and measure the actual route before cutting the cable.
M09 and two-wire M11 use separately sourced 120 Ω shielded twisted pair. Check the sensor power route separately.
Reference layout shows functions and identifiers. Confirm actual openings, gland fit and cable rating. Use the approved drilling drawing for dimensions.
Cable and label schedule R03, pp. 1–4 / Cabinet assembly drawings, pp. 1–2 / Functional layout for tracing
CABLE INDEX
EN / 01 OF 80
End-tower cabinet openings
End-tower cabinet / Two numbered bottom openings and two roof feeders. Select a route to trace its conductors.
CABINET ORIENTATION / END TOWER
End-tower cabinet openings
End-tower cabinet / Two numbered bottom openings and two roof feeders. Select a route to trace its conductors.
End-tower cabinet opening map
Two individually numbered bottom openings and two top antenna feeds. Separate diagrams show the one-cable and split fault wiring options.
END-TOWER CABINET · REFERENCE FRONT VIEW
2 bottom cable openings / 2 top antenna feed-throughs
END-TOWER RETROFIT CABINET
Identify supply and fault wiring independently.
AC
Supply and PE
Incoming AC and 12 V distribution.
RF
GPS B and radio
End position and local radio traffic.
I/O
Tower fault inputs
X1–X4 with local input returns.
E-BR1 RADIO 2.4GHZ
Tower-to-main radio coax
E-BR2 GPS B
Moving end-tower positioning coax
E01
E02
E01 AC POWER IN 110VAC · 3 × 1.5 mm²
E02 TOWER FAULTS · 8 × 0.75 mm²
E02 · SINGLE-CABLE INSTALLATION
Mark the jacket E02 TOWER FAULTS at both ends.
Tower signals
Four pairs · signal and return
8 × 0.75 mm²
End-tower cabinet
Local relay or approved dry input
Powered sources use the approved isolation relay coil pair.
Approved dry contacts use the documented X input and local return route.
Open the E02 single-cable wiring sheet →
E02 · SEPARATE ISOLATION BOX
Use a separate 8 × 0.75 mm² cable on each side where fitted.
Tower signals
Up to four powered pairs
Isolation box
K1–K4 relays
End-tower cabinet
X1–X4 and returns
MACHINE SIDE jacket suffix
4 × A1/A2 coil pairs
CONTROLLER SIDE jacket suffix
4 × 11/14 dry pairs through opening 02
Open machine-side wiring →
Open isolated return wiring →
The tower cabinet schedule has two bottom openings.
See main-cabinet M09 for the optional cable monitor →
Drawn by function. Confirm gasket and cable gland placement on the enclosure and use the approved drilling drawing for dimensions.
Cable and label schedule R03, pp. 4–5 / Cabinet assembly drawings, pp. 11–16
CABLE INDEX
EN / 02 OF 80
Field cables and roof feeders
Main cabinet 01–11, end tower 01–02 and the five roof feeders.
CONTENTS / CABLE INDEX
Field cables and roof feeders
Main cabinet 01–11, end tower 01–02 and the five roof feeders.
M01
Main cabinet supply and protective earth
09
M02
Start, stop and returned run status
10
M03
Forward command and feedback
11
M04
Reverse command and feedback
12
M05
Original cabinet fault feedback
13
M06
Local mode and takeover feedback
14
M07
Main sprinkler supply and feedback
15
M08
Single end gun and feedback
16
M09
Cable monitor data pair
17
M10
Reserved standard travel-speed cable
18
M11
Optional agricultural sensor cable
19
E01
End-tower supply and protective earth
20
E02
Four end-tower fault inputs
21
E02-S
Tower faults · single external cable
22
E02-M
Tower faults · machine-side cable
23
E02-C
Tower faults · controller-side cable
24
AR1
Cellular gateway antenna feeder
25
AR2
Pivot-center GPS A feeder
26
AR3
Main local-radio antenna feeder
27
BR1
Tower local-radio antenna feeder
28
BR2
End-tower GPS B antenna feeder
29
Field cables
Separate-box variants
Main cabinet interior
Tower interior & records
Cable index / Select a line to open its page
CABLE INDEX
EN / 03 OF 80
Separate-box cable variants
Choose these sheets only where a main feedback relay is in a separate enclosure. Each physical segment has its own page.
INDEX-BOX / CABLE INDEX
Separate-box cable variants
Choose these sheets only where a main feedback relay is in a separate enclosure. Each physical segment has its own page.
M02-C
Run / stop · controller side cable
30
M02-M
Run / stop · machine side cable
31
M03-C
Forward · controller side cable
32
M03-M
Forward · machine side cable
33
M04-C
Reverse · controller side cable
34
M04-M
Reverse · machine side cable
35
M05-C
Panel fault · controller side cable
36
M05-M
Panel fault · machine side cable
37
M06-C
Local mode · controller side cable
38
M06-M
Local mode · machine side cable
39
M07-C
Span spray · controller side cable
40
M07-M
Span spray · machine side cable
41
M08-C
End gun · controller side cable
42
M08-M
End gun · machine side cable
43
Field cables
Separate-box variants
Main cabinet interior
Tower interior & records
Cable index / Select a line to open its page
CABLE INDEX
EN / 04 OF 80
Inside the main cabinet
Follow an internal device lead or terminal group. The optional monitoring enclosure is shown on its own sheets.
INDEX-MAIN / CABLE INDEX
Inside the main cabinet
Follow an internal device lead or terminal group. The optional monitoring enclosure is shown on its own sheets.
MI01
Main cabinet AC feed-through and earth
44
MI02
24 V DC supply distribution
45
MI03
Main controller 24 V branch
46
MI04A
Cellular gateway 24 V branch
47
MI04B
Main local radio 24 V branch
48
MI05
Controller to gateway Ethernet
49
MI06
Controller to main radio RS-485
50
MI07A
Run and direction command pigtails
51
MI07B
End-gun and span-spray command pigtails
52
MI08
Feedback strip to controller inputs
53
MI09A
Feedback returns to block 1
54
MI09B
Feedback returns to block 2
55
MI10A
DGND to return block 1
56
MI10B
Return block 1 to return block 2
57
MI11
Isolated run and direction feedback
58
MI12
Isolated end-gun and panel fault feedback
59
MI13
Isolated local mode and span-spray feedback
60
MI14A
Option cabinet · isolated measurement pair
61
MI14B
Option cabinet · acquisition module power
62
Field cables
Separate-box variants
Main cabinet interior
Tower interior & records
Cable index / Select a line to open its page
CABLE INDEX
EN / 05 OF 80
Inside the end tower and field records
Follow the tower low-voltage and communication circuits, then record commissioning and as-built terminals.
INDEX-TOWER / CABLE INDEX
Inside the end tower and field records
Follow the tower low-voltage and communication circuits, then record commissioning and as-built terminals.
EI01
End tower AC feed-through and earth
63
EI02
12 V DC supply distribution
64
EI03A
Tower local radio 12 V branch
65
EI03B
GPS B receiver 12 V branch
66
EI03C
Tower input collector 12 V branch
67
EI04A
Collector input COM positive lead
68
EI04B
0 V feed to the tower return block
69
EI05A
RS-485 · Tower local radio
70
EI05B
RS-485 · GPS B receiver
71
EI05C
RS-485 · Tower input collector
72
EI06A
Fault feed-through signal pigtails
73
EI06B
Fault feed-through return pigtails
74
EI07
Optional tower isolation contact pigtails
75
COM-1
Commission travel, stop and local control
76
COM-2
Commission water, data and fitted options
77
RECORD
As-built cable and core record
78
HANDOVER
Acceptance and handover
79
EVIDENCE
What the project records establish
80
Field cables
Separate-box variants
Main cabinet interior
Tower interior & records
Cable index / Select a line to open its page
CABLE INDEX
EN / 06 OF 80
Prepare, identify and prove the cable
Start with the approved circuit, the jacket ID and the two physical ends.
METHOD / USING THE GUIDE
Prepare, identify and prove the cable
Start with the approved circuit, the jacket ID and the two physical ends.
1
Isolate both ends
A qualified electrician identifies all energy sources, including separate tower
supplies and backfeeds. Follow the site isolation procedure and verify
absence of voltage before touching conductors.
2
Choose the actual cable
Read the core count and conductor area on the jacket. Measure the installed
route. Verify protection, voltage rating, gland fit, bend allowance and outdoor
suitability for the actual duty.
3
Label the jacket and each core
Apply matching jacket and core marks at both ends. A four-core cable needs
two jacket labels and eight core labels. Internal leads marked “(function)”
use descriptive names when the project gives no printed core ID.
4
Read the two sides of the rail
On these drawings, the upper connection of a feed-through goes inside the
box and the lower one goes to the field. Both belong to one terminal.
Adjacent terminals are separate.
5
Terminate and ring out
With both ends isolated, disconnect sensitive equipment for the planned
check. Prove each core by tag. Follow the fitted terminal’s strip length and
torque, then gently tug each conductor.
6
Resolve every open end
A dashed trace ending in a ring marks a site decision. Identify and record
the actual terminal, matching return and normal state. Cap each reserved or
spare core separately until assigned.
Assembly drawings, pp. 1–3, 8, 11–12 / Cable and label schedule R03, pp. 1–5
CABLE INDEX
EN / 07 OF 80
Identify the feedback interface
The main cabinet uses DI and DGND. The end tower uses X inputs and its own local 0 V return.
INTERFACES / USING THE GUIDE
Identify the feedback interface
The main cabinet uses DI and DGND. The end tower uses X inputs and its own local 0 V return.
Powered indication through an isolation relay
Original indication circuit
Isolation relay
Retrofit feedback circuit
Signal to verify
A1
11
Input via XF or tower X
Its matching return
A2
14
DGND or local 0 V return
COIL
DRY CONTACT
The coil and its dry contact are electrically separate. Terminal 12 is unused in the reference normally-open arrangement.
A compatible dry contact already exists
Existing volt-free contact
Reference input pair
Contact end 1
Assigned input via XF or tower X
Contact end 2
Matched DGND or local 0 V return
Check the interface before connection
Document whether the original signal is powered or volt-free, its normal state and the matching return. Choose the approved circuit and use its conductor
labels. Machine voltage stays on the coil side.
Main cable schedule R02 / Assembly drawings, pp. 8, 14 and 16 / R03, p. 5
CABLE INDEX
EN / 08 OF 80
Main cabinet supply and protective earth
Reference 110 V AC branch to the 24 V DC power supply
M01 / MAIN CABINET
Main cabinet supply and protective earth
Reference 110 V AC branch to the 24 V DC power supply
MAIN RETROFIT CABINET
Design incoming AC branch feeds a 24 V DC supply.
ORIGINAL CONTROL CABINET
Branch position, protection and terminals to be verified.
VERIFY THE SOURCE BEFORE TERMINATING
Design input is 110 V AC. Verify actual control-supply voltage.
L
Approved protected line branch
N
Verified return of that same branch
PE
Dedicated protective-earth conductor
Record the approved locations before landing any lead.
24 V DC POWER SUPPLY
AC INPUT
L
N
CABINET PE BAR
X0-L
X0-N
PE
L
N
PE
Protected
line
Same branch
return
Protective
earth point
CABLE JACKET CUTAWAY
M01-L
M01-L
M01-N
M01-N
M01-PE
M01-PE
Bottom opening 01 · AC entry
Original branch entry · verify
M01 AC POWER IN 110VAC
M01 AC POWER IN 110VAC
Reference cable · 3 × 1.5 mm², including green/yellow PE
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Approve the branch
Isolate both ends and verify absence of voltage.
Check the source and its dedicated protection.
Verify L, its paired return and the earth point.
2
Label and route
Use the shown jacket label for an approved 110 V feed.
Mark L, N and PE at each end before landing.
Use bottom opening 01 and the matching terminals.
3
Check before use
Verify protective bonding and conductor identity.
Record AC input and the 24 V DC output.
Reconnect loads only under the approved procedure.
BENCH TEST
No cable-specific continuity, protective-earth or voltage measurement is recorded for this main supply lead.
FIELD CHECK
Approved source, protection, terminal position and protective continuity must be recorded on the actual machine.
Main conductor schedule R02 • rows 7–9 | Cable schedule R03 | Assembly pp. 2–4
CABLE INDEX
EN / 09 OF 80
Start, stop and returned run status
Four cores carry the remote start and stop request and a separate run feedback circuit.
M02 / MAIN CABINET
Start, stop and returned run status
Four cores carry the remote start and stop request and a separate run feedback circuit.
M02 physical cable and reference termination drawing
Four cores carry the remote start and stop request and a separate run feedback circuit. The original cabinet endpoints are open until approved.
MAIN RETROFIT CABINET
Reference assembly terminal locations
ORIGINAL CABINET
Locate the drawing references and verify the actual circuit.
FIELD LANDINGS OPEN
CONTROLLER
CH1 start and stop request
COM
NO
XC strip
XC-1a
XC-1b
K1 RUN FEEDBACK RELAY
MACHINE COIL
ISOLATED DRY CONTACT
A1
A2
11
14
XF-1
XF-1R
CONTROLLER
DI1 input
DGND return
M02-K1-11
M02-K1-14
INDEPENDENT RUN STATUS
1MF / 1MR spare auxiliary contacts
One approved run state for both directions.
ORIGINAL START AND STOP
Trace SA3 and ST-1. ST-1 contacts 23–25.
Retain the stop chain. Keep the 24 V branch intact.
Bottom exit 02
Field entry · confirm on site
M02 RUN / STOP · 4 × 0.75 mm² CONTROL CABLE
Same jacket ID and same core IDs at both ends
M02-K1-A2
M02-K1-A2
RUN RETURN
Terminal to confirm
M02-K1-A1
M02-K1-A1
RUN SIGNAL
Terminal to confirm
M02-CH1-NO
M02-CH1-NO
RUN REQUEST
Terminal to confirm
M02-CH1-COM
M02-CH1-COM
RUN COMMON
Terminal to confirm
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find opening 02
Isolate and prove both cabinets de-energized.
Mark the jacket and each core at both ends.
Ring out all four cores with the ends isolated.
2
Trace the original controls
Trace SA3 and ST-1. Retain the original stop chain.
Confirm a separate run signal in both directions.
Confirm its matching return and relay coil rating.
3
Prove run and stop
Use the signed design and approved test load first.
Prove local stop, remote stop and no sudden start.
Witness travel and match DI1 to actual standstill.
BENCH TEST
13 Nov 2026: DI1 closed on forward and reverse starts and opened after a stop on the existing contact-harness fixture.
FIELD CHECK
Confirm the original hold/release design, independent run source and original stop authority. Never bridge ST-1 contacts 23 and 25.
R02 main cable schedule, rows 10–13 and tests 09–11 / R03 opening 02 and dry-contact labels / 13 Nov board bench
CABLE INDEX
EN / 10 OF 80
Forward command and feedback
One four-core cable carries the forward request and the separate forward-status circuit. • 4 × 0.75 mm²
M03 / MAIN CABINET
Forward command and feedback
One four-core cable carries the forward request and the separate forward-status circuit. • 4 × 0.75 mm²
M03 forward cable from retrofit cabinet to original irrigation cabinet
Four labeled cores follow the U-shaped cable route. The retrofit assembly terminals are documented. The original circuit references are open and require field confirmation. A relay separates the original feedback circuit from the controller input.
MAIN RETROFIT CABINET
Reference assembly terminal locations
ORIGINAL CABINET
Locate the drawing references and verify the actual circuit.
CONTROLLER
CH2 forward request
COM
NO
K2 FORWARD FEEDBACK RELAY
MACHINE COIL
ISOLATED DRY CONTACT
A1
A2
11
14
XC strip
XF
CONTROLLER
DI2 input
DGND return
HL5 FORWARD INDICATION
3SS SELECTOR REFERENCE
Drawing candidates. Verify status and return.
wire 23 at TB2-2 · wire 11 at TB1-1
Drawing traces only. Changeover design required.
FIELD LANDINGS OPEN
Bottom exit 03
Field entry · confirm on site
M03 FORWARD · 4 × 0.75 mm² CONTROL CABLE
Same jacket ID and same core IDs at both ends
XC-2a
XC-2b
XF-2
XF-2R
M03-CH2-COM
M03-CH2-COM
REMOTE COMMON
Terminal to confirm
M03-CH2-NO
M03-CH2-NO
REMOTE REQUEST
Terminal to confirm
M03-K2-A1
M03-K2-A1
TB3-1
wire 1 · HL5 signal
M03-K2-A2
M03-K2-A2
TB3-4
wire 4 · same HL5 return
M03-K2-11
M03-K2-14
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify both pairs
Isolate both cabinets. Mark the jacket M03 FORWARD.
Fit the same core ID at each end. Check continuity
end to end with both ends disconnected.
2
Trace before landing
Trace the selector in all positions. Verify the HL5 signal,
its matching return and the feedback relay coil rating.
Land the four field ends against the signed drawing.
3
Prove forward travel
After field approval, test the request and DI2 separately.
Witness forward travel. Check reverse feedback stays off.
Stop the pivot and confirm that DI2 clears.
BENCH TEST
13 Nov 2026 · With the bench jumper harness, DI2 closed on forward start and opened after stop.
FIELD CHECK
Confirm the selector circuit, interlocks and feedback pair before landing the field ends.
Main cable schedule R02, rows 14–17 / Forward wiring example R03, pp. 2–3, 5 / Original main cabinet schematic
CABLE INDEX
EN / 11 OF 80
Reverse command and feedback
The reverse request and the independently returned reverse status use separate pairs in the same cable.
M04 / MAIN CABINET
Reverse command and feedback
The reverse request and the independently returned reverse status use separate pairs in the same cable.
M04 physical cable and reference termination drawing
The reverse request and the independently returned reverse status use separate pairs in the same cable. The original cabinet endpoints are open until approved.
MAIN RETROFIT CABINET
Reference assembly terminal locations
ORIGINAL CABINET
Locate the drawing references and verify the actual circuit.
FIELD LANDINGS OPEN
CONTROLLER
CH3 reverse request
COM
NO
XC strip
XC-3a
XC-3b
K3 REVERSE FEEDBACK RELAY
MACHINE COIL
ISOLATED DRY CONTACT
A1
A2
11
14
XF-3
XF-3R
CONTROLLER
DI3 input
DGND return
M04-K3-11
M04-K3-14
HL4 REVERSE INDICATION
1MR auxiliary contact feeds HL4 on the drawing
Verify the status and its matching circuit return.
3SS SELECTOR REFERENCE
wire 23 at TB2-2 · wire 12 at TB1-2
Drawing traces only. Changeover design required.
Bottom exit 04
Field entry · confirm on site
M04 REVERSE · 4 × 0.75 mm² CONTROL CABLE
Same jacket ID and same core IDs at both ends
M04-K3-A2
M04-K3-A2
TB3-4
wire 4 · same HL4 return
M04-K3-A1
M04-K3-A1
TB3-2
wire 2 · HL4 signal
M04-CH3-NO
M04-CH3-NO
REMOTE REVERSE
Terminal to confirm
M04-CH3-COM
M04-CH3-COM
REMOTE COMMON
Terminal to confirm
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find opening 04
Isolate and prove both cabinets de-energized.
Match the jacket and core labels at both ends.
Use an isolated test to verify each core.
2
Trace the two circuits
Record the actual 3SS switch positions and paths.
Verify both HL4 wires and the relay coil rating.
Use the signed reverse and interlock drawing.
3
Prove reverse and stop
At standstill, test the request and DI3 separately.
Witness reverse travel and check DI2 stays off.
Stop and verify DI3 drops and travel ceases.
BENCH TEST
13 Nov 2026: DI3 closed on reverse start and opened at stop in the existing contact-harness test.
FIELD CHECK
Verify the original selector circuit, interlock, HL4 source and return before landing. Observe actual machine movement and stop.
R02 main cable schedule, rows 18–21 and tests 08–10 / R03 opening 04 and dry-contact labels / 13 Nov board bench
CABLE INDEX
EN / 12 OF 80
Original cabinet fault feedback
Two cores bring an approved original-panel fault indication to the isolated controller input.
M05 / MAIN CABINET
Original cabinet fault feedback
Two cores bring an approved original-panel fault indication to the isolated controller input.
M05 physical cable and reference termination drawing
Two cores bring an approved original-panel fault indication to the isolated controller input. The original cabinet endpoints are open until approved.
MAIN RETROFIT CABINET
Reference assembly terminal locations
ORIGINAL CABINET
Locate the drawing references and verify the actual circuit.
FIELD LANDINGS OPEN
INPUT-ONLY CABLE
One field signal and return
No controller output on this cable.
The relay contact supplies status
to DI5 in the retrofit cabinet.
K5 FAULT FEEDBACK RELAY
MACHINE COIL
ISOLATED DRY CONTACT
A1
A2
11
14
XF-5
XF-5R
CONTROLLER
DI5 input
DGND return
M05-K5-11
M05-K5-14
CHOOSE AN INDEPENDENT FAULT SOURCE
Trace the alarm output and its matching return.
HL6 indicates the safety circuit. Choose a separate fault source.
Bottom exit 05
Field entry · confirm on site
M05 PANEL FAULT · 2 × 0.75 mm² CONTROL CABLE
Same jacket ID and same core IDs at both ends
M05-K5-A2
M05-K5-A2
FAULT SIGNAL RETURN
Terminal to confirm
M05-K5-A1
M05-K5-A1
PANEL FAULT SIGNAL
Terminal to confirm
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find opening 05
Isolate both cabinets. Identify the two cores.
Fit the same core labels at both cable ends.
Check the cable with both ends disconnected.
2
Identify the indication
Confirm how healthy, fault and power loss read.
Verify the matching return and coil rating.
Land only on the approved isolation circuit.
3
Prove the fault and reset
Use the approved test point to simulate a fault.
Check the DI5 change and the returned App state.
Reset, check recovery and record what DI5 covers.
BENCH TEST
R02 specifies an isolated relay test. No DI5 fault-loop result is recorded in the 13 Nov board test.
FIELD CHECK
Keep the original safety chain in service. Keep DI5 unassigned until an independent fault source is approved and verified.
R02 main cable schedule, rows 22–23 and tests 03 and 16 / R03 opening 05 and dry-contact labels
CABLE INDEX
EN / 13 OF 80
Local mode and takeover feedback
Two cores bring the independent local-mode indication to DI6 where a suitable source is fitted.
M06 / MAIN CABINET
Local mode and takeover feedback
Two cores bring the independent local-mode indication to DI6 where a suitable source is fitted.
M06 physical cable and reference termination drawing
Two cores bring the independent local-mode indication to DI6 where a suitable source is fitted. The original cabinet endpoints are open until approved.
MAIN RETROFIT CABINET
Reference assembly terminal locations
ORIGINAL CABINET
Locate the drawing references and verify the actual circuit.
FIELD LANDINGS OPEN
INPUT-ONLY CABLE
One field signal and return
No controller output on this cable.
The relay contact supplies status
to DI6 in the retrofit cabinet.
K6 MODE FEEDBACK RELAY
MACHINE COIL
ISOLATED DRY CONTACT
A1
A2
11
14
XF-6
XF-6R
CONTROLLER
DI6 input
DGND return
M06-K6-11
M06-K6-14
CHOOSE AN INDEPENDENT MODE SOURCE
Use a verified auxiliary contact if a local/remote selector is fitted.
Direction selection and cabinet power are not mode indications.
Bottom exit 06
Field entry · confirm on site
M06 LOCAL MODE · 2 × 0.75 mm² CONTROL CABLE
Same jacket ID and same core IDs at both ends
M06-K6-A2
M06-K6-A2
MODE SIGNAL RETURN
Terminal to confirm
M06-K6-A1
M06-K6-A1
LOCAL MODE SIGNAL
Terminal to confirm
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find opening 06
Isolate and prove both cabinets de-energized.
Label the jacket and two cores at both ends.
Ring out the isolated cores and mark any reserve.
2
Confirm the selector route
Record the actual behavior in every mode.
Find the separate indication and its own return.
Land the mode pair only after approval.
3
Prove local authority
Prove the original local stop and takeover.
Where fitted, match DI6 to the actual selector.
Check mode changes do not start travel.
BENCH TEST
R02 specifies a mode indication test. No DI6 installed-selector result is recorded in the 13 Nov board test.
FIELD CHECK
Verify original local stop and takeover before remote movement. Keep DI6 unassigned unless fitted and approved.
R02 main cable schedule, rows 24–25 and tests 10 and 16 / R03 opening 06 and dry-contact labels
CABLE INDEX
EN / 14 OF 80
Main sprinkler supply and feedback
The supply permit and an independent pump, valve or flow indication use separate pairs.
M07 / MAIN CABINET
Main sprinkler supply and feedback
The supply permit and an independent pump, valve or flow indication use separate pairs.
M07 physical cable and reference termination drawing
The supply permit and an independent pump, valve or flow indication use separate pairs. The original cabinet endpoints are open until approved.
MAIN RETROFIT CABINET
Reference assembly terminal locations
ORIGINAL CABINET
Locate the drawing references and verify the actual circuit.
FIELD LANDINGS OPEN
CONTROLLER
CH5 main supply request
COM
NO
XC strip
XC-5a
XC-5b
K7 SUPPLY FEEDBACK RELAY
MACHINE COIL
ISOLATED DRY CONTACT
A1
A2
11
14
XF-7
XF-7R
CONTROLLER
DI7 input
DGND return
M07-K7-11
M07-K7-14
INDEPENDENT WATER STATUS
Choose approved valve, pump or flow status.
Record which state the input actually measures.
MAIN WATER SUPPLY PERMIT
Confirm the chosen pump or main-valve input.
The original drawing has no designated span valve.
Bottom exit 07
Field entry · confirm on site
M07 SPAN SPRAY · 4 × 0.75 mm² CONTROL CABLE
Same jacket ID and same core IDs at both ends
M07-K7-A2
M07-K7-A2
WATER RETURN
Terminal to confirm
M07-K7-A1
M07-K7-A1
WATER STATUS
Terminal to confirm
M07-CH5-NO
M07-CH5-NO
PERMIT INPUT
Terminal to confirm
M07-CH5-COM
M07-CH5-COM
PERMIT COMMON
Terminal to confirm
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find opening 07
Isolate all related circuits and label both ends.
Ring out the two command and two status cores.
Keep any unassigned cores insulated separately.
2
Identify permit and status
Approve the supply permit and separate status.
Record whether status means valve, pump or flow.
Use the signed drawing before landing the cores.
3
Prove flow separately
Test CH5 and DI7 separately with an approved load.
Witness actual flow when water is allowed to run.
Record the request, return and water result.
BENCH TEST
The board output CH5 closed with DI7 open and timed out on the contact bench. No pump, valve or water was connected.
FIELD CHECK
Keep these cores isolated until the supply permit and independent feedback are approved. Remove any temporary bench feedback jumper.
R02 main cable schedule, rows 26–29 / R03 opening 07 and dry-contact labels / Board supply-feedback timeout record
CABLE INDEX
EN / 15 OF 80
Single end gun and feedback
The original switch can be traced. Remote changeover and separate valve or booster-pump status require approval.
M08 / MAIN CABINET
Single end gun and feedback
The original switch can be traced. Remote changeover and separate valve or booster-pump status require approval.
M08 physical cable and reference termination drawing
The original switch can be traced. Remote changeover and separate valve or booster-pump status require approval. The original cabinet endpoints are open until approved.
MAIN RETROFIT CABINET
Reference assembly terminal locations
ORIGINAL CABINET
Locate the drawing references and verify the actual circuit.
FIELD LANDINGS OPEN
CONTROLLER
CH4 end-gun request
COM
NO
XC strip
XC-4a
XC-4b
K4 END GUN FEEDBACK RELAY
MACHINE COIL
ISOLATED DRY CONTACT
A1
A2
11
14
XF-4
XF-4R
CONTROLLER
DI4 input
DGND return
M08-K4-11
M08-K4-14
INDEPENDENT END-GUN STATUS
Choose valve or booster-pump status.
The original switch output is a command signal.
ORIGINAL END-GUN SWITCH
wire 25 upstream · wire 5 at TB3-6 downstream
Trace only. Use the approved changeover design.
Bottom exit 08
Field entry · confirm on site
M08 END GUN · 4 × 0.75 mm² CONTROL CABLE
Same jacket ID and same core IDs at both ends
M08-K4-A2
M08-K4-A2
GUN RETURN
Terminal to confirm
M08-K4-A1
M08-K4-A1
GUN STATUS
Terminal to confirm
M08-CH4-NO
M08-CH4-NO
GUN REQUEST
Terminal to confirm
M08-CH4-COM
M08-CH4-COM
GUN COMMON
Terminal to confirm
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find opening 08
Isolate both cabinets. Label the four cores.
Trace wires 25 and 5 at the original gun switch.
Check continuity on the isolated cable.
2
Approve the two routes
Use the signed break-before-make changeover.
Verify the independent status and its return.
Keep the original stop protection in service.
3
Prove remote shutoff
In remote mode, test off with the local switch on.
Check that DI4 follows the approved status source.
Record valve, pump and actual spray separately.
BENCH TEST
13 Nov 2026: DI4 followed CH4 on and off on the contact-harness fixture. No spray was tested.
FIELD CHECK
Confirm original switch routing and independent status. In remote mode, prove the end gun shuts off while the local switch is on.
R02 main cable schedule, rows 30–33 and tests 12–13 / R03 opening 08 and dry-contact labels / 13 Nov board bench
CABLE INDEX
EN / 16 OF 80
Cable monitor data pair
Optional RS-485 interface through main cabinet opening 09
M09 / MAIN CABINET
Cable monitor data pair
Optional RS-485 interface through main cabinet opening 09
MAIN RETROFIT CABINET
RS-485 branch point at the controller.
CABLE MONITOR ENCLOSURE
Confirm the fitted connector, data settings and power.
MAIN CONTROLLER · RS-485
MONITOR DATA PORT
Fitted device pin assignment to be verified.
A+
A+ branch point
A
B−
B− branch point
B
Match printed A and B.
SEPARATE DETECTION CIRCUIT
Original power conductors shown schematically.
Use a separately approved detection and power drawing.
M09 carries reader data only. Detection topology is site-specific.
CABLE JACKET CUTAWAY
M09-485-A
M09-485-A
M09-485-B
M09-485-B
Bottom opening 09 · data cable
Remote interface entry · verify
M09 CABLE MONITOR
M09 CABLE MONITOR
Two-wire reference · 120 Ω shielded twisted pair · 2 × 0.75 mm²
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify data points
Find the controller’s 485 A+ and B− branch.
Confirm monitor A/B pinout and serial settings.
Approve monitor supply and shield arrangement.
2
Tag both ends
Print the M09 jacket label at both cable ends.
Label A and B individually before termination.
Keep the data pair clear of power wiring.
3
Verify separately
Check identity and continuity of the data pair.
Use the separate approved detection drawing.
Test alarm delivery, mains loss and reconnection.
BENCH TEST
Software simulation covered power loss, monitor faults and reconnection. The physical detection circuit still needs testing.
FIELD CHECK
Approve the separate monitored-cable detection circuit, power and backup. M09 is the data path only.
Main conductor schedule R02 • opening 9 | Cable schedule R03 | Assembly pp. 9–10 and 17
CABLE INDEX
EN / 17 OF 80
Reserved standard travel-speed cable
Four-core cable to hold until speed switching is approved
M10 / MAIN CABINET
Reserved standard travel-speed cable
Four-core cable to hold until speed switching is approved
MAIN RETROFIT CABINET
Speed relay and output channel are unassigned.
ORIGINAL CONTROL CABINET
Approve the local and remote changeover before using M10.
ORIGINAL TIMER TRACE REFERENCES
Find and verify the original 1TR timer and its wiring.
1
Wire 26
2
Wire 25
3
Wire 3
4
Wire 4
Switching pair: 2 and 3. Wire 3 goes to TB3-3 in the drawing.
Supply pair: 1 and 4. This inset identifies the original circuit.
RESERVED SPEED OUTPUT
Physical relay and switching contacts pending.
SELECTED PATH · TO BE DESIGNED
Original local timer retention required.
COM
TBC
NO
TBC
CABLE JACKET CUTAWAY
M10-SPD-COM
M10-SPD-COM
M10-SPD-NO
M10-SPD-NO
M10-SPARE3
M10-SPARE3
M10-SPARE4
M10-SPARE4
Bottom opening 10 · reserved
Approved selector entry · pending
M10 SPEED CONTROL
M10 SPEED CONTROL
4 × 1.0 mm² four-core control cable · both ends isolated until approved
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Trace original timer
Locate 1TR switching terminals 2 and 3.
Verify wires 25 and 3, including TB3-3.
Check supply pair 1/4 independently.
2
Prepare the cable
Mark M10 SPEED CONTROL at both cable ends.
Apply COM, NO and applicable spare labels.
Insulate each unassigned end individually.
3
Release and test
Approve relay channel and local/remote circuit.
Prove switching on an approved test load.
Record run-window timing and physical travel.
BENCH TEST
Software timing at 25%, 50% and 100% plus stop was tested. The record covers no physical speed relay or machine travel.
FIELD CHECK
Keep all reserved cores isolated until a physical channel and the local/remote switching design are approved.
Main conductor schedule R02 • opening 10 | Cable schedule R03 | Standard travel-speed simulation
CABLE INDEX
EN / 18 OF 80
Optional agricultural sensor cable
Two-wire data pair or device-specific approved four-core cable
M11 / MAIN CABINET
Optional agricultural sensor cable
Two-wire data pair or device-specific approved four-core cable
MAIN RETROFIT CABINET
RS-485 branch point at the controller.
PROBE OR APPROVED ADAPTER
Confirm the fitted connector, data settings and power.
MAIN CONTROLLER · RS-485
DEVICE DATA PORT
Fitted device pin assignment to be verified.
A+
A+ branch point
A
B−
B− branch point
B
Match printed A and B.
OPTIONAL FOUR-CORE BUILD
Select only for a compatible device and approved cable.
M11-485-A
M11-485-A
M11-485-B
M11-485-B
M11-SPARE3
M11-SPARE3
M11-SPARE4
M11-SPARE4
Cap unused cores 3 and 4 individually at both ends.
If extra cores supply power, verify pinout and amend the approved labels.
CABLE JACKET CUTAWAY
M11-485-A
M11-485-A
M11-485-B
M11-485-B
Bottom opening 11 · data cable
Remote interface entry · verify
M11 SENSORS
M11 SENSORS
Two-wire reference · 120 Ω shielded twisted pair · 2 × 0.75 mm²
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify the probe
Confirm A/B pinout, profile and sensor voltage.
Verify a suitable adapter for analog readings.
Approve the device supply separately.
2
Choose the cable
Use the approved two-wire pair if power is separate.
Use a compatible four-core cable when specified.
Cap and mark only genuinely unused spare cores.
3
Validate the sample
Check continuity and branch communication.
Confirm address and reading profile with Admin.
Compare the fresh sample to a known reference.
BENCH TEST
Serial simulator only. Read profiles and software processing were exercised. The fitted sensor and wiring still need testing.
FIELD CHECK
Approve each probe or adapter pinout, power and profile, then verify a fresh reading and its units after reconnecting.
Main conductor schedule R02 • opening 11 | Cable schedule R03 | Sensor serial simulation
CABLE INDEX
EN / 19 OF 80
End-tower supply and protective earth
Reference 110 V AC branch to the tower 12 V DC power supply
E01 / END TOWER
End-tower supply and protective earth
Reference 110 V AC branch to the tower 12 V DC power supply
END-TOWER RETROFIT CABINET
Design incoming AC branch feeds a 12 V DC supply.
ORIGINAL TOWER SUPPLY
Branch position, protection and terminals to be verified.
VERIFY THE SOURCE BEFORE TERMINATING
Design input is 110 V AC. Verify actual control-supply voltage.
L
Approved protected line branch
N
Verified return of that same branch
PE
Dedicated protective-earth conductor
Record the approved locations before landing any lead.
12 V DC POWER SUPPLY
AC INPUT
L
N
CABINET PE BAR
L
N
PE
L
N
PE
Protected
line
Same branch
return
Protective
earth point
CABLE JACKET CUTAWAY
E01-L
E01-L
E01-N
E01-N
E01-PE
E01-PE
Bottom opening 01 · AC entry
Original branch entry · verify
E01 AC POWER IN 110VAC
E01 AC POWER IN 110VAC
Reference cable · 3 × 1.5 mm², including green/yellow PE
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Approve tower supply
Identify and isolate the approved source.
Confirm voltage, branch protection and return.
Verify the original tower protective earth point.
2
Tag, route and bond
Mark E01 jacket and each core on both ends.
Use tower bottom opening 01 for AC entry.
Separate the AC group from the fault input group.
3
Check before use
Verify protective continuity and source pairing.
Record the 12 V DC supply before loading.
Check voltage again with approved loads fitted.
BENCH TEST
No cable-specific continuity, protective-earth or voltage measurement is recorded for this tower supply lead.
FIELD CHECK
Record the actual tower supply and branch protection, protective bond and measured DC output before connecting the loads.
Cable schedule R03 • E01 | Cabinet assembly pp. 11–14
CABLE INDEX
EN / 20 OF 80
Four end-tower fault inputs
The separate isolation box uses two eight-core cables. Trace one relay and its matching pair at a time. • 8 × 0.75 mm² per cable
E02 / END TOWER
Four end-tower fault inputs
The separate isolation box uses two eight-core cables. Trace one relay and its matching pair at a time. • 8 × 0.75 mm² per cable
END-TOWER CABINET
Door open · viewed from the front
12 V DC
Power supply
+V
−V
TOWER INPUT COLLECTOR
Lower screw strip · actual left-to-right sequence
X4
X3
X2
X1
COM
A/H
B/L
+
−
+12 V distribution
1
2
3
4
5
0 V distribution
1
2
3
4
5
0 V lead 5 → 1
+12 V 5 → COM
LOCAL 0 V CONTACT-RETURN BLOCK
1
2
3
4
5
FAULT FEED-THROUGH
STRIP
Upper side · inside cabinet
Lower side · field cable
L
N
PE
X1
PAIR 1
E02-K1-11
0 V
E02-K1-14
X2
PAIR 2
E02-K2-11
0 V
E02-K2-14
X3
PAIR 3
E02-K3-11
0 V
E02-K3-14
X4
PAIR 4
E02-K4-11
0 V
E02-K4-14
AC group
Trace by wire ID.
Colors are illustrative.
BOTTOM OPENING 02
E02 cable gland
OPTIONAL ISOLATION BOX
Dry contacts
Site-side coils
ORIGINAL TOWER FAULT SITES
Source locations schematic · actual positions pending
Trace each source and return on site.
K1
ISOLATED
A2
A1
E02-K1-11
E02-K1-A1
E02-K1-14
E02-K1-A2
VERIFY
K2
ISOLATED
A2
A1
E02-K2-11
E02-K2-A1
E02-K2-14
E02-K2-A2
VERIFY
K3
ISOLATED
A2
A1
E02-K3-11
E02-K3-A1
E02-K3-14
E02-K3-A2
VERIFY
K4
ISOLATED
A2
A1
E02-K4-11
E02-K4-A1
E02-K4-14
E02-K4-A2
VERIFY
Sites may be distributed across the machine.
E02 TOWER FAULTS CONTROLLER SIDE
E02 TOWER FAULTS MACHINE SIDE
X1–X4 use isolated contacts only. Wire 11 to X and 14 to its 0 V return.
A1 is the assigned fault signal. A2 is its matched return.
One eight-core cable per side. Confirm the actual openings and routes on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify the fault source
Isolate the circuits. Assign each physical tower to X1–X4.
Trace its signal and matching return. Record both ends.
Continuity-check each tagged core before landing it.
2
Wire one relay at a time
Land the approved signal at A1 and its return at A2.
On the dry side, take 11 to X and 14 to its 0 V return.
Only the isolated contact feeds the input pair.
3
Prove alarm and reset
After approval, test each assigned tower separately.
Match its alarm and reset to the tower shown in the App.
Verify that the other three inputs keep their prior state.
BENCH TEST
12 Nov 2026 · X1 read active when connected to local 0 V and cleared when released on the bench.
FIELD CHECK
Confirm all four tower assignments, source terminals and end-to-end alarm returns.
Cable label schedule R03, E02 / Cabinet assembly drawings, pp. 12, 14–16 / Isolated input test record, 12 Nov 2026
CABLE INDEX
EN / 21 OF 80
Tower faults · single external cable
Cabinet-mounted isolation relays · powered signals to A1/A2
E02-S / END TOWER
Tower faults · single external cable
Cabinet-mounted isolation relays · powered signals to A1/A2
ORIGINAL TOWER FAULT LOCATIONS
Source locations schematic. Trace each actual signal and return.
END-TOWER RETROFIT CABINET
Isolation relays are mounted inside the tower input cabinet.
K1
A1
A2
K2
A1
A2
K3
A1
A2
K4
A1
A2
CABINET-MOUNTED ISOLATION RELAY COILS
Isolated contacts connect separately inside this cabinet.
CONFIRM ORIGINAL FAULT SIGNALS
A single cable carries all four powered pairs to the tower cabinet.
A1
Assigned tower fault signal
A2
Matched return of that same circuit
Fault sources may be distributed across the machine.
K1–K4 are relay IDs. Assign actual tower IDs on site.
K1 route
S
R
K2 route
S
R
K3 route
S
R
K4 route
S
R
S = possible source · R = its matched return
CABLE JACKET CUTAWAY
E02-K1-A1
E02-K1-A1
E02-K1-A2
E02-K1-A2
E02-K2-A1
E02-K2-A1
E02-K2-A2
E02-K2-A2
E02-K3-A1
E02-K3-A1
E02-K3-A2
E02-K3-A2
E02-K4-A1
E02-K4-A1
E02-K4-A2
E02-K4-A2
Original locations · entry plan pending
Bottom opening 02 · into end-tower cabinet
E02 TOWER FAULTS
E02 TOWER FAULTS
Single cable · 8 × 0.75 mm² eight-core control cable
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify each tower
Mark actual tower IDs for the four relay routes.
Verify each powered signal and its matched return.
Approve the circuit voltage and relay coil ratings.
2
Label and route
Print E02 TOWER FAULTS at both cable ends.
Tag all eight A1/A2 cores at both ends.
Enter through bottom opening 02 and land at coils.
3
Verify both sides
Check each relay response and return separately.
Check the cabinet’s isolated contacts to X1–X4.
Verify reset and the actual tower shown in the App.
BENCH TEST
The isolated input module was tested on X1. The eight-core field lead and four fitted relay coils await their own tests.
FIELD CHECK
Record the physical source and return for each tower and verify each X channel using the approved isolated contact path.
Cable schedule R03 • pp. 4–5 | Cabinet assembly pp. 12, 14–16
CABLE INDEX
EN / 22 OF 80
Tower faults · machine-side cable
Separate isolation enclosure option · powered source to relay coils
E02-M / END TOWER
Tower faults · machine-side cable
Separate isolation enclosure option · powered source to relay coils
ORIGINAL TOWER FAULT LOCATIONS
Source locations schematic. Trace each actual signal and return.
SEPARATE ISOLATION ENCLOSURE
Coil-side A1/A2 terminals only.
K1
A1
A2
K2
A1
A2
K3
A1
A2
K4
A1
A2
OTHER SIDE OF EACH RELAY STAYS ELECTRICALLY SEPARATE
CONFIRM ORIGINAL FAULT SIGNALS
All eight cores belong to the powered machine-side cable.
A1
Assigned tower fault signal
A2
Matched return of that same circuit
Fault sources may be distributed across the machine.
K1–K4 are relay IDs. Assign actual tower IDs on site.
K1 route
S
R
K2 route
S
R
K3 route
S
R
K4 route
S
R
S = possible source · R = its matched return
CABLE JACKET CUTAWAY
E02-K1-A1
E02-K1-A1
E02-K1-A2
E02-K1-A2
E02-K2-A1
E02-K2-A1
E02-K2-A2
E02-K2-A2
E02-K3-A1
E02-K3-A1
E02-K3-A2
E02-K3-A2
E02-K4-A1
E02-K4-A1
E02-K4-A2
E02-K4-A2
Original locations · entry plan pending
One eight-core cable · isolation box entry
E02 TOWER FAULTS MACHINE SIDE
E02 TOWER FAULTS MACHINE SIDE
Reference segment · 8 × 0.75 mm² eight-core control cable
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify each tower
Record actual tower IDs against the four routes.
Identify each powered signal and matched return.
Approve protection, voltage and coil ratings.
2
Label both ends
Use E02 TOWER FAULTS MACHINE SIDE on jackets.
Put each matching A1/A2 label at both ends.
Keep this cable separate from the dry-contact lead.
3
Test the assigned paths
Verify source and return for each isolated route.
Prove the intended relay responds and resets.
Record the actual sources in the as-built drawing.
BENCH TEST
No end-to-end test of this machine-side eight-core cable or its four original fault circuits is recorded.
FIELD CHECK
S/R locations are shown schematically. Identify the actual tower, source and same-circuit return before connecting.
Cable schedule R03 • pp. 4–5 | Cabinet assembly pp. 14–16
CABLE INDEX
EN / 23 OF 80
Tower faults · controller-side cable
Separate isolation enclosure option · dry contacts to fault terminals
E02-C / END TOWER
Tower faults · controller-side cable
Separate isolation enclosure option · dry contacts to fault terminals
END-TOWER RETROFIT CABINET
Lower fault terminals lead to X1–X4 and local 0 V.
SEPARATE ISOLATION ENCLOSURE
Isolated dry contacts 11/14 only.
K1
11
14
K2
11
14
K3
11
14
K4
11
14
OTHER SIDE OF EACH RELAY STAYS ELECTRICALLY SEPARATE
DRY CONTACTS TO TOWER INPUTS
Keep the input/return pairs separate across the cable.
11
Goes to the matching X input
14
Goes to that pair’s local 0 V return
Collector COM is connected to the cabinet’s local +12 V.
0 V distribution 5 feeds return block 1. See sheet EI04B.
Prove each input against its assigned physical tower.
INPUT COLLECTOR LOWER STRIP
X4
X3
X2
X1
COM
A/H
B/L
+
−
+12 V
LOCAL 0 V RETURN
1
2
3
4
5
X1
0 V
X2
0 V
X3
0 V
X4
0 V
CABLE JACKET CUTAWAY
E02-K1-11
E02-K1-11
E02-K1-14
E02-K1-14
E02-K2-11
E02-K2-11
E02-K2-14
E02-K2-14
E02-K3-11
E02-K3-11
E02-K3-14
E02-K3-14
E02-K4-11
E02-K4-11
E02-K4-14
E02-K4-14
Bottom opening 02 · fault cable
One eight-core cable · isolation box entry
E02 TOWER FAULTS CONTROLLER SIDE
E02 TOWER FAULTS CONTROLLER SIDE
Reference segment · 8 × 0.75 mm² eight-core control cable
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify the dry side
Find isolated relay terminals 11 and 14.
Trace matching X-input and local 0 V terminals.
Keep the relay coil circuit separate.
2
Tag and land
Mark the CONTROLLER SIDE jacket at both ends.
Match every E02 11/14 label at both ends.
Use end-tower bottom opening 02.
3
Check alarms
Prove one fault and reset at a time.
Verify the actual tower and displayed X channel.
Record positioning and alarm evidence separately.
BENCH TEST
Isolated USB testing verified X1 on/off. A separate power-cycle test retained module address 2 and 9600 baud.
FIELD CHECK
Verify the reported tower and live position. The shown input circuit uses local +12 V COM and isolated 11/14 contacts.
Cable schedule R03 • pp. 4–5 | Cabinet assembly pp. 12, 14–16 | X1 standalone USB record
CABLE INDEX
EN / 24 OF 80
Cellular gateway antenna feeder
One complete coaxial feeder. Apply the full jacket label to both ends.
AR1 / ANTENNA FEEDERS
Cellular gateway antenna feeder
One complete coaxial feeder. Apply the full jacket label to both ends.
MAIN CABINET
Cellular gateway
LTE
Port on the fitted device
M-AR1 4G LTE
M-AR1 4G LTE
ROOF GLAND
Check the fitted position.
Confirm mating
connector on site.
Cellular antenna
Antenna mating connector • factory-terminated coax
Keep labels clear of connector threads and seals.
Main cabinet roof · verify the actual exit
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the correct port
Identify the device port marked LTE.
Use the lead specified for this antenna.
2
Route the whole feeder
Use the approved roof exit and weather seal.
Confirm clearance, bend radius and slack.
3
Label and prove
Apply the same jacket label at both ends.
Check the commissioned signal for this link.
BENCH TEST
The gateway used 4G on the board. Antenna connector and link margin were not separately recorded.
FIELD CHECK
Connector family and roof-hole position require hardware confirmation. Match both ends to the fitted feeder.
Assembly drawing, p. 5. R02, roof entry. R03, p. 4, complete feeder labels.
CABLE INDEX
EN / 25 OF 80
Pivot-center GPS A feeder
One complete coaxial feeder. Apply the full jacket label to both ends.
AR2 / ANTENNA FEEDERS
Pivot-center GPS A feeder
One complete coaxial feeder. Apply the full jacket label to both ends.
MAIN CABINET
Cellular gateway
GPS
Port on the fitted device
M-AR2 GPS A
M-AR2 GPS A
ROOF GLAND
Check the fitted position.
Confirm mating
connector on site.
GPS A antenna
Antenna mating connector • factory-terminated coax
Keep labels clear of connector threads and seals.
Main cabinet roof · verify the actual exit
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the correct port
Identify the device port marked GPS.
Use the lead specified for this antenna.
2
Route the whole feeder
Use the approved roof exit and weather seal.
Confirm clearance, bend radius and slack.
3
Label and prove
Apply the same jacket label at both ends.
Check the commissioned signal for this link.
BENCH TEST
The project recorded real position A. The feeder connector and signal margin were not separately recorded.
FIELD CHECK
Connector family and roof-hole position require hardware confirmation. Match both ends to the fitted feeder.
Assembly drawing, p. 5. R02, roof entry. R03, p. 4, complete feeder labels.
CABLE INDEX
EN / 26 OF 80
Main local-radio antenna feeder
One complete coaxial feeder. Apply the full jacket label to both ends.
AR3 / ANTENNA FEEDERS
Main local-radio antenna feeder
One complete coaxial feeder. Apply the full jacket label to both ends.
MAIN CABINET
Main local radio
ANT
Port on the fitted device
M-AR3 RADIO 2.4GHZ
M-AR3 RADIO 2.4GHZ
ROOF GLAND
Check the fitted position.
Confirm mating
connector on site.
Main 2.4 GHz antenna
Antenna mating connector • factory-terminated coax
Keep labels clear of connector threads and seals.
Main cabinet roof · verify the actual exit
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the correct port
Identify the device port marked ANT.
Use the lead specified for this antenna.
2
Route the whole feeder
Use the approved roof exit and weather seal.
Confirm clearance, bend radius and slack.
3
Label and prove
Apply the same jacket label at both ends.
Check the commissioned signal for this link.
BENCH TEST
Project board records show the radio pair carried position B. There is no feeder-specific RF test in the record.
FIELD CHECK
Connector family and roof-hole position require hardware confirmation. Match both ends to the fitted feeder.
Assembly drawing, p. 5. R02, roof entry. R03, p. 4, complete feeder labels.
CABLE INDEX
EN / 27 OF 80
Tower local-radio antenna feeder
One complete coaxial feeder. Apply the full jacket label to both ends.
BR1 / ANTENNA FEEDERS
Tower local-radio antenna feeder
One complete coaxial feeder. Apply the full jacket label to both ends.
END-TOWER CABINET
Tower local radio
ANT
Port on the fitted device
E-BR1 RADIO 2.4GHZ
E-BR1 RADIO 2.4GHZ
ROOF GLAND
Check the fitted position.
Confirm mating
connector on site.
Tower 2.4 GHz antenna
Antenna mating connector • factory-terminated coax
Keep labels clear of connector threads and seals.
Tower cabinet roof · verify the actual exit
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the correct port
Identify the device port marked ANT.
Use the lead specified for this antenna.
2
Route the whole feeder
Use the approved roof exit and weather seal.
Confirm clearance, bend radius and slack.
3
Label and prove
Apply the same jacket label at both ends.
Check the commissioned signal for this link.
BENCH TEST
Project board records show the radio pair carried position B. There is no feeder-specific RF test in the record.
FIELD CHECK
Connector family and roof-hole position require hardware confirmation. Match both ends to the fitted feeder.
Assembly drawing, p. 15. R03, p. 4, complete feeder labels.
CABLE INDEX
EN / 28 OF 80
End-tower GPS B antenna feeder
One complete coaxial feeder. Apply the full jacket label to both ends.
BR2 / ANTENNA FEEDERS
End-tower GPS B antenna feeder
One complete coaxial feeder. Apply the full jacket label to both ends.
END-TOWER CABINET
GPS B receiver
ANT
Port on the fitted device
E-BR2 GPS B
E-BR2 GPS B
ROOF GLAND
Check the fitted position.
Confirm mating
connector on site.
GPS B antenna
Antenna mating connector • factory-terminated coax
Keep labels clear of connector threads and seals.
Tower cabinet roof · verify the actual exit
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the correct port
Identify the device port marked ANT.
Use the lead specified for this antenna.
2
Route the whole feeder
Use the approved roof exit and weather seal.
Confirm clearance, bend radius and slack.
3
Label and prove
Apply the same jacket label at both ends.
Check the commissioned signal for this link.
BENCH TEST
The project recorded real position B. The feeder connector and signal margin were not separately recorded.
FIELD CHECK
Connector family and roof-hole position require hardware confirmation. Match both ends to the fitted feeder.
Assembly drawing, p. 15. R03, p. 4, complete feeder labels.
CABLE INDEX
EN / 29 OF 80
Run / stop · controller side cable
M02 RUN / STOP CONTROLLER SIDE • 4 × 0.75 mm² • Optional separate-box installation
M02-C / SEPARATE RELAY BOX
Run / stop · controller side cable
M02 RUN / STOP CONTROLLER SIDE • 4 × 0.75 mm² • Optional separate-box installation
MAIN RETROFIT CABINET
SEPARATE ISOLATION BOX
XC-1a · CH1
COM
Approved
through-point
VERIFY
M02-CH1-COM
M02-CH1-COM
XC-1b · CH1 NO
Approved
through-point
VERIFY
M02-CH1-NO
M02-CH1-NO
XF-1 → DI1
K1 contact 11
M02-K1-11
M02-K1-11
XF-1R → DGND
K1 contact 14
M02-K1-14
M02-K1-14
Main bottom opening 02
Relay-box entry · site layout
M02 RUN / STOP CONTROLLER SIDE
M02 RUN / STOP CONTROLLER SIDE
Main bottom opening 02 to relay box • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Mark this segment
Identify main cabinet opening 02 and relay K1.
Apply the CONTROLLER SIDE jacket ID at both ends.
Mark every core before termination.
2
Land the dry pair
Land K1 contact 11 at XF-1 and 14 at XF-1R.
Follow XF-1 to DI1. Follow XF-1R to DGND.
Confirm any command through-points on site.
3
Test at the controller
Check core continuity with both ends disconnected.
Operate the approved test contact and observe DI1.
Release the test contact and verify the normal state.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and the independent run return on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M02 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 30 OF 80
Run / stop · machine side cable
M02 RUN / STOP MACHINE SIDE • 4 × 0.75 mm² • Optional separate-box installation
M02-M / SEPARATE RELAY BOX
Run / stop · machine side cable
M02 RUN / STOP MACHINE SIDE • 4 × 0.75 mm² • Optional separate-box installation
SEPARATE ISOLATION BOX
ORIGINAL MACHINE CABINET
Approved
through-point
VERIFY
Request
common
VERIFY
M02-CH1-COM
M02-CH1-COM
Approved
through-point
VERIFY
Request input
VERIFY
M02-CH1-NO
M02-CH1-NO
K1 coil A1
Run status
source
VERIFY
M02-K1-A1
M02-K1-A1
K1 coil A2
Matching circuit
return
VERIFY
M02-K1-A2
M02-K1-A2
Relay-box entry · site layout
Original cabinet entry · site layout
M02 RUN / STOP MACHINE SIDE
M02 RUN / STOP MACHINE SIDE
Relay box to original machine cabinet • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Trace the original circuit
Trace the start, hold and stop chain.
Confirm its status source and same-circuit return.
Record the actual original-panel terminals.
2
Label and land
Apply the MACHINE SIDE jacket ID at both ends.
Use A1/A2 only for the verified relay coil circuit.
Confirm any command through-points on site.
3
Verify this segment
With ends isolated, ring out each core by its tag.
Prove that the coil follows the actual field status.
Witness the independent run return.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and the independent run return on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M02 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 31 OF 80
Forward · controller side cable
M03 FORWARD CONTROLLER SIDE • 4 × 0.75 mm² • Optional separate-box installation
M03-C / SEPARATE RELAY BOX
Forward · controller side cable
M03 FORWARD CONTROLLER SIDE • 4 × 0.75 mm² • Optional separate-box installation
MAIN RETROFIT CABINET
SEPARATE ISOLATION BOX
XC-2a · CH2
COM
Approved
through-point
VERIFY
M03-CH2-COM
M03-CH2-COM
XC-2b · CH2 NO
Approved
through-point
VERIFY
M03-CH2-NO
M03-CH2-NO
XF-2 → DI2
K2 contact 11
M03-K2-11
M03-K2-11
XF-2R → DGND
K2 contact 14
M03-K2-14
M03-K2-14
Main bottom opening 03
Relay-box entry · site layout
M03 FORWARD CONTROLLER SIDE
M03 FORWARD CONTROLLER SIDE
Main bottom opening 03 to relay box • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Mark this segment
Identify main cabinet opening 03 and relay K2.
Apply the CONTROLLER SIDE jacket ID at both ends.
Mark every core before termination.
2
Land the dry pair
Land K2 contact 11 at XF-2 and 14 at XF-2R.
Follow XF-2 to DI2. Follow XF-2R to DGND.
Confirm any command through-points on site.
3
Test at the controller
Check core continuity with both ends disconnected.
Operate the approved test contact and observe DI2.
Release the test contact and verify the normal state.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and forward status on DI2 on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M03 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 32 OF 80
Forward · machine side cable
M03 FORWARD MACHINE SIDE • 4 × 0.75 mm² • Optional separate-box installation
M03-M / SEPARATE RELAY BOX
Forward · machine side cable
M03 FORWARD MACHINE SIDE • 4 × 0.75 mm² • Optional separate-box installation
SEPARATE ISOLATION BOX
ORIGINAL MACHINE CABINET
Approved
through-point
VERIFY
Request
common
VERIFY
M03-CH2-COM
M03-CH2-COM
Approved
through-point
VERIFY
Request input
VERIFY
M03-CH2-NO
M03-CH2-NO
K2 coil A1
HL5 status
candidate
VERIFY
M03-K2-A1
M03-K2-A1
K2 coil A2
Matching circuit
return
VERIFY
M03-K2-A2
M03-K2-A2
Relay-box entry · site layout
Original cabinet entry · site layout
M03 FORWARD MACHINE SIDE
M03 FORWARD MACHINE SIDE
Relay box to original machine cabinet • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Trace the original circuit
Trace 3SS wire 23 and forward wire 11.
Confirm its status source and same-circuit return.
Record the actual original-panel terminals.
2
Label and land
Apply the MACHINE SIDE jacket ID at both ends.
Use A1/A2 only for the verified relay coil circuit.
Confirm any command through-points on site.
3
Verify this segment
With ends isolated, ring out each core by its tag.
Prove that the coil follows the actual field status.
Witness forward status on DI2.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and forward status on DI2 on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M03 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 33 OF 80
Reverse · controller side cable
M04 REVERSE CONTROLLER SIDE • 4 × 0.75 mm² • Optional separate-box installation
M04-C / SEPARATE RELAY BOX
Reverse · controller side cable
M04 REVERSE CONTROLLER SIDE • 4 × 0.75 mm² • Optional separate-box installation
MAIN RETROFIT CABINET
SEPARATE ISOLATION BOX
XC-3a · CH3
COM
Approved
through-point
VERIFY
M04-CH3-COM
M04-CH3-COM
XC-3b · CH3 NO
Approved
through-point
VERIFY
M04-CH3-NO
M04-CH3-NO
XF-3 → DI3
K3 contact 11
M04-K3-11
M04-K3-11
XF-3R → DGND
K3 contact 14
M04-K3-14
M04-K3-14
Main bottom opening 04
Relay-box entry · site layout
M04 REVERSE CONTROLLER SIDE
M04 REVERSE CONTROLLER SIDE
Main bottom opening 04 to relay box • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Mark this segment
Identify main cabinet opening 04 and relay K3.
Apply the CONTROLLER SIDE jacket ID at both ends.
Mark every core before termination.
2
Land the dry pair
Land K3 contact 11 at XF-3 and 14 at XF-3R.
Follow XF-3 to DI3. Follow XF-3R to DGND.
Confirm any command through-points on site.
3
Test at the controller
Check core continuity with both ends disconnected.
Operate the approved test contact and observe DI3.
Release the test contact and verify the normal state.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and reverse status on DI3 on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M04 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 34 OF 80
Reverse · machine side cable
M04 REVERSE MACHINE SIDE • 4 × 0.75 mm² • Optional separate-box installation
M04-M / SEPARATE RELAY BOX
Reverse · machine side cable
M04 REVERSE MACHINE SIDE • 4 × 0.75 mm² • Optional separate-box installation
SEPARATE ISOLATION BOX
ORIGINAL MACHINE CABINET
Approved
through-point
VERIFY
Request
common
VERIFY
M04-CH3-COM
M04-CH3-COM
Approved
through-point
VERIFY
Request input
VERIFY
M04-CH3-NO
M04-CH3-NO
K3 coil A1
HL4 status
candidate
VERIFY
M04-K3-A1
M04-K3-A1
K3 coil A2
Matching circuit
return
VERIFY
M04-K3-A2
M04-K3-A2
Relay-box entry · site layout
Original cabinet entry · site layout
M04 REVERSE MACHINE SIDE
M04 REVERSE MACHINE SIDE
Relay box to original machine cabinet • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Trace the original circuit
Trace 3SS wire 23 and reverse wire 12.
Confirm its status source and same-circuit return.
Record the actual original-panel terminals.
2
Label and land
Apply the MACHINE SIDE jacket ID at both ends.
Use A1/A2 only for the verified relay coil circuit.
Confirm any command through-points on site.
3
Verify this segment
With ends isolated, ring out each core by its tag.
Prove that the coil follows the actual field status.
Witness reverse status on DI3.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and reverse status on DI3 on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M04 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 35 OF 80
Panel fault · controller side cable
M05 PANEL FAULT CONTROLLER SIDE • 2 × 0.75 mm² • Optional separate-box installation
M05-C / SEPARATE RELAY BOX
Panel fault · controller side cable
M05 PANEL FAULT CONTROLLER SIDE • 2 × 0.75 mm² • Optional separate-box installation
MAIN RETROFIT CABINET
SEPARATE ISOLATION BOX
XF-5 → DI5
K5 contact 11
M05-K5-11
M05-K5-11
XF-5R → DGND
K5 contact 14
M05-K5-14
M05-K5-14
Main bottom opening 05
Relay-box entry · site layout
M05 PANEL FAULT CONTROLLER SIDE
M05 PANEL FAULT CONTROLLER SIDE
Main bottom opening 05 to relay box • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Mark this segment
Identify main cabinet opening 05 and relay K5.
Apply the CONTROLLER SIDE jacket ID at both ends.
Mark every core before termination.
2
Land the dry pair
Land K5 contact 11 at XF-5 and 14 at XF-5R.
Follow XF-5 to DI5. Follow XF-5R to DGND.
Keep both cores in the isolated input circuit.
3
Test at the controller
Check core continuity with both ends disconnected.
Operate the approved test contact and observe DI5.
Release the test contact and verify the normal state.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and the independent panel fault return on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M05 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 36 OF 80
Panel fault · machine side cable
M05 PANEL FAULT MACHINE SIDE • 2 × 0.75 mm² • Optional separate-box installation
M05-M / SEPARATE RELAY BOX
Panel fault · machine side cable
M05 PANEL FAULT MACHINE SIDE • 2 × 0.75 mm² • Optional separate-box installation
SEPARATE ISOLATION BOX
ORIGINAL MACHINE CABINET
K5 coil A1
Panel fault source
VERIFY
M05-K5-A1
M05-K5-A1
K5 coil A2
Matching circuit
return
VERIFY
M05-K5-A2
M05-K5-A2
Relay-box entry · site layout
Original cabinet entry · site layout
M05 PANEL FAULT MACHINE SIDE
M05 PANEL FAULT MACHINE SIDE
Relay box to original machine cabinet • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Trace the original circuit
Verify which signal means a general panel fault.
Confirm its status source and same-circuit return.
Record the actual original-panel terminals.
2
Label and land
Apply the MACHINE SIDE jacket ID at both ends.
Use A1/A2 only for the verified relay coil circuit.
Match the circuit to the fitted coil rating.
3
Verify this segment
With ends isolated, ring out each core by its tag.
Prove that the coil follows the actual field status.
Witness the independent panel fault return.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and the independent panel fault return on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M05 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 37 OF 80
Local mode · controller side cable
M06 LOCAL MODE CONTROLLER SIDE • 2 × 0.75 mm² • Optional separate-box installation
M06-C / SEPARATE RELAY BOX
Local mode · controller side cable
M06 LOCAL MODE CONTROLLER SIDE • 2 × 0.75 mm² • Optional separate-box installation
MAIN RETROFIT CABINET
SEPARATE ISOLATION BOX
XF-6 → DI6
K6 contact 11
M06-K6-11
M06-K6-11
XF-6R → DGND
K6 contact 14
M06-K6-14
M06-K6-14
Main bottom opening 06
Relay-box entry · site layout
M06 LOCAL MODE CONTROLLER SIDE
M06 LOCAL MODE CONTROLLER SIDE
Main bottom opening 06 to relay box • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Mark this segment
Identify main cabinet opening 06 and relay K6.
Apply the CONTROLLER SIDE jacket ID at both ends.
Mark every core before termination.
2
Land the dry pair
Land K6 contact 11 at XF-6 and 14 at XF-6R.
Follow XF-6 to DI6. Follow XF-6R to DGND.
Keep both cores in the isolated input circuit.
3
Test at the controller
Check core continuity with both ends disconnected.
Operate the approved test contact and observe DI6.
Release the test contact and verify the normal state.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and the local mode return on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M06 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 38 OF 80
Local mode · machine side cable
M06 LOCAL MODE MACHINE SIDE • 2 × 0.75 mm² • Optional separate-box installation
M06-M / SEPARATE RELAY BOX
Local mode · machine side cable
M06 LOCAL MODE MACHINE SIDE • 2 × 0.75 mm² • Optional separate-box installation
SEPARATE ISOLATION BOX
ORIGINAL MACHINE CABINET
K6 coil A1
Local mode source
VERIFY
M06-K6-A1
M06-K6-A1
K6 coil A2
Matching circuit
return
VERIFY
M06-K6-A2
M06-K6-A2
Relay-box entry · site layout
Original cabinet entry · site layout
M06 LOCAL MODE MACHINE SIDE
M06 LOCAL MODE MACHINE SIDE
Relay box to original machine cabinet • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Trace the original circuit
Identify a separate mode indication contact.
Confirm its status source and same-circuit return.
Record the actual original-panel terminals.
2
Label and land
Apply the MACHINE SIDE jacket ID at both ends.
Use A1/A2 only for the verified relay coil circuit.
Match the circuit to the fitted coil rating.
3
Verify this segment
With ends isolated, ring out each core by its tag.
Prove that the coil follows the actual field status.
Witness the local mode return.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and the local mode return on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M06 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 39 OF 80
Span spray · controller side cable
M07 SPAN SPRAY CONTROLLER SIDE • 4 × 0.75 mm² • Optional separate-box installation
M07-C / SEPARATE RELAY BOX
Span spray · controller side cable
M07 SPAN SPRAY CONTROLLER SIDE • 4 × 0.75 mm² • Optional separate-box installation
MAIN RETROFIT CABINET
SEPARATE ISOLATION BOX
XC-5a · CH5
COM
Approved
through-point
VERIFY
M07-CH5-COM
M07-CH5-COM
XC-5b · CH5 NO
Approved
through-point
VERIFY
M07-CH5-NO
M07-CH5-NO
XF-7 → DI7
K7 contact 11
M07-K7-11
M07-K7-11
XF-7R → DGND
K7 contact 14
M07-K7-14
M07-K7-14
Main bottom opening 07
Relay-box entry · site layout
M07 SPAN SPRAY CONTROLLER SIDE
M07 SPAN SPRAY CONTROLLER SIDE
Main bottom opening 07 to relay box • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Mark this segment
Identify main cabinet opening 07 and relay K7.
Apply the CONTROLLER SIDE jacket ID at both ends.
Mark every core before termination.
2
Land the dry pair
Land K7 contact 11 at XF-7 and 14 at XF-7R.
Follow XF-7 to DI7. Follow XF-7R to DGND.
Confirm any command through-points on site.
3
Test at the controller
Check core continuity with both ends disconnected.
Operate the approved test contact and observe DI7.
Release the test contact and verify the normal state.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and water status under an approved wet test on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M07 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 40 OF 80
Span spray · machine side cable
M07 SPAN SPRAY MACHINE SIDE • 4 × 0.75 mm² • Optional separate-box installation
M07-M / SEPARATE RELAY BOX
Span spray · machine side cable
M07 SPAN SPRAY MACHINE SIDE • 4 × 0.75 mm² • Optional separate-box installation
SEPARATE ISOLATION BOX
ORIGINAL MACHINE CABINET
Approved
through-point
VERIFY
Request
common
VERIFY
M07-CH5-COM
M07-CH5-COM
Approved
through-point
VERIFY
Request input
VERIFY
M07-CH5-NO
M07-CH5-NO
K7 coil A1
Independent
water status
VERIFY
M07-K7-A1
M07-K7-A1
K7 coil A2
Matching circuit
return
VERIFY
M07-K7-A2
M07-K7-A2
Relay-box entry · site layout
Original cabinet entry · site layout
M07 SPAN SPRAY MACHINE SIDE
M07 SPAN SPRAY MACHINE SIDE
Relay box to original machine cabinet • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Trace the original circuit
Trace the pump or valve permit and its feedback.
Confirm its status source and same-circuit return.
Record the actual original-panel terminals.
2
Label and land
Apply the MACHINE SIDE jacket ID at both ends.
Use A1/A2 only for the verified relay coil circuit.
Confirm any command through-points on site.
3
Verify this segment
With ends isolated, ring out each core by its tag.
Prove that the coil follows the actual field status.
Witness water status under an approved wet test.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and water status under an approved wet test on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M07 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 41 OF 80
End gun · controller side cable
M08 END GUN CONTROLLER SIDE • 4 × 0.75 mm² • Optional separate-box installation
M08-C / SEPARATE RELAY BOX
End gun · controller side cable
M08 END GUN CONTROLLER SIDE • 4 × 0.75 mm² • Optional separate-box installation
MAIN RETROFIT CABINET
SEPARATE ISOLATION BOX
XC-4a · CH4
COM
Approved
through-point
VERIFY
M08-CH4-COM
M08-CH4-COM
XC-4b · CH4 NO
Approved
through-point
VERIFY
M08-CH4-NO
M08-CH4-NO
XF-4 → DI4
K4 contact 11
M08-K4-11
M08-K4-11
XF-4R → DGND
K4 contact 14
M08-K4-14
M08-K4-14
Main bottom opening 08
Relay-box entry · site layout
M08 END GUN CONTROLLER SIDE
M08 END GUN CONTROLLER SIDE
Main bottom opening 08 to relay box • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Mark this segment
Identify main cabinet opening 08 and relay K4.
Apply the CONTROLLER SIDE jacket ID at both ends.
Mark every core before termination.
2
Land the dry pair
Land K4 contact 11 at XF-4 and 14 at XF-4R.
Follow XF-4 to DI4. Follow XF-4R to DGND.
Confirm any command through-points on site.
3
Test at the controller
Check core continuity with both ends disconnected.
Operate the approved test contact and observe DI4.
Release the test contact and verify the normal state.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and the end-gun feedback and actual spray on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M08 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 42 OF 80
End gun · machine side cable
M08 END GUN MACHINE SIDE • 4 × 0.75 mm² • Optional separate-box installation
M08-M / SEPARATE RELAY BOX
End gun · machine side cable
M08 END GUN MACHINE SIDE • 4 × 0.75 mm² • Optional separate-box installation
SEPARATE ISOLATION BOX
ORIGINAL MACHINE CABINET
Approved
through-point
VERIFY
Request
common
VERIFY
M08-CH4-COM
M08-CH4-COM
Approved
through-point
VERIFY
Request input
VERIFY
M08-CH4-NO
M08-CH4-NO
K4 coil A1
Valve or
booster status
VERIFY
M08-K4-A1
M08-K4-A1
K4 coil A2
Matching circuit
return
VERIFY
M08-K4-A2
M08-K4-A2
Relay-box entry · site layout
Original cabinet entry · site layout
M08 END GUN MACHINE SIDE
M08 END GUN MACHINE SIDE
Relay box to original machine cabinet • Confirm unnumbered entry locations on site.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Trace the original circuit
Trace switch wire 25 and wire 5 at TB3-6.
Confirm its status source and same-circuit return.
Record the actual original-panel terminals.
2
Label and land
Apply the MACHINE SIDE jacket ID at both ends.
Use A1/A2 only for the verified relay coil circuit.
Confirm any command through-points on site.
3
Verify this segment
With ends isolated, ring out each core by its tag.
Prove that the coil follows the actual field status.
Witness the end-gun feedback and actual spray.
BENCH TEST
This separate-box field cable has no recorded end-to-end bench test.
FIELD CHECK
Confirm the cable route, core continuity and the end-gun feedback and actual spray on the installed machine.
Cable labels R03, pp. 3 and 5 / Main terminal schedule R02, M08 / Cabinet assembly, pp. 6–8
CABLE INDEX
EN / 43 OF 80
Main cabinet AC feed-through and earth
Three separate pigtails feed the 24 V DC supply and the protective-earth rail.
MI01 / MAIN INTERIOR
Main cabinet AC feed-through and earth
Three separate pigtails feed the 24 V DC supply and the protective-earth rail.
Inside main cabinet · separated AC group
Lower AC and PE terminals
DC supply and PE rail
X0-L, inside
Supply AC L
L (function)
L (function)
X0-N, inside
Supply AC N
N (function)
N (function)
PE terminal, inside
Dedicated PE rail
PE (function)
PE (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Locate
Find L, N and PE on the lower rail.
Work with both sides isolated and verified.
2
Trace
Follow L and N to the supply input.
Follow PE to the dedicated bonding rail.
3
Prove
Check each path and the earth continuity.
Record the approved branch protection.
BENCH TEST
The assembly drawing identifies both ends. No electrical measurement of these specific leads is recorded.
FIELD CHECK
Verify the AC branch, protection and any enclosure bonding against the installed machine.
Assembly drawing, pp. 2–3. R02, opening 1.
CABLE INDEX
EN / 44 OF 80
24 V DC supply distribution
Place the positive and return leads into separate distribution blocks.
MI02 / MAIN INTERIOR
24 V DC supply distribution
Place the positive and return leads into separate distribution blocks.
Inside main cabinet · DC duct
DC power supply
DC distribution blocks
DC +V
+24 V block,
position 1
+24 V (function)
+24 V (function)
DC −V
0 V block, position
1
0 V (function)
0 V (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify
Find +V and −V on the supply.
The block positions follow the assembly drawing.
2
Connect
Connect the positive lead to its own block.
Run the 0 V lead to the separate return block.
3
Prove
Verify polarity at the blocks before loading.
Record voltage with the fitted loads connected.
BENCH TEST
The assembly drawing identifies both ends. No electrical measurement of these specific leads is recorded.
FIELD CHECK
Verify actual wire gauge, polarity and voltage. Positive and return distribution blocks stay separate.
Assembly drawing, p. 4.
CABLE INDEX
EN / 45 OF 80
Main controller 24 V branch
Follow the positive feed through its own fuse and the return directly to the device.
MI03 / MAIN INTERIOR
Main controller 24 V branch
Follow the positive feed through its own fuse and the return directly to the device.
Inside main cabinet · protected DC branch
24 V distribution blocks
Branch fuse
Main controller
+24 V block, position 2
0 V block, position 2
+24 V feed (function)
+24 V load (function)
Supply end
Load end
0 V return (function)
Power +
Power −
The two positive leads meet only through the branch fuse. Trace the return directly to 0 V.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify
Locate position 2 on both DC blocks.
Confirm the fuse holder and protection rating.
2
Trace the branch
Trace the two positive pieces via the fuse.
Trace the 0 V lead directly to the device.
3
Prove polarity
Check the marked device terminals before power.
Record voltage at the device under load.
BENCH TEST
No branch-specific bench voltage or continuity reading is recorded for this fused feed.
FIELD CHECK
Confirm actual device pin numbering and the approved fuse before connecting the branch.
Assembly drawing, p. 4, position 2
CABLE INDEX
EN / 46 OF 80
Cellular gateway 24 V branch
Follow the positive feed through its own fuse and the return directly to the device.
MI04A / MAIN INTERIOR
Cellular gateway 24 V branch
Follow the positive feed through its own fuse and the return directly to the device.
Inside main cabinet · protected DC branch
24 V distribution blocks
Branch fuse
Cellular gateway
+24 V block, position 3
0 V block, position 3
+24 V feed (function)
+24 V load (function)
Supply end
Load end
0 V return (function)
Power plug pin 2 (+)
Power plug pin 1 (−)
The two positive leads meet only through the branch fuse. Trace the return directly to 0 V.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify
Locate position 3 on both DC blocks.
Confirm the fuse holder and protection rating.
2
Trace the branch
Trace the two positive pieces via the fuse.
Trace the 0 V lead directly to the device.
3
Prove polarity
Check the marked device terminals before power.
Record voltage at the device under load.
BENCH TEST
No branch-specific bench voltage or continuity reading is recorded for this fused feed.
FIELD CHECK
Confirm actual device pin numbering and the approved fuse before connecting the branch.
Assembly drawing, p. 4, position 3
CABLE INDEX
EN / 47 OF 80
Main local radio 24 V branch
Follow the positive feed through its own fuse and the return directly to the device.
MI04B / MAIN INTERIOR
Main local radio 24 V branch
Follow the positive feed through its own fuse and the return directly to the device.
Inside main cabinet · protected DC branch
24 V distribution blocks
Branch fuse
Main local radio
+24 V block, position 4
0 V block, position 4
+24 V feed (function)
+24 V load (function)
Supply end
Load end
0 V return (function)
Four-pin plug 1 (+)
Four-pin plug 2 (−)
The two positive leads meet only through the branch fuse. Trace the return directly to 0 V.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify
Locate position 4 on both DC blocks.
Confirm the fuse holder and protection rating.
2
Trace the branch
Trace the two positive pieces via the fuse.
Trace the 0 V lead directly to the device.
3
Prove polarity
Check the marked device terminals before power.
Record voltage at the device under load.
BENCH TEST
No branch-specific bench voltage or continuity reading is recorded for this fused feed.
FIELD CHECK
Confirm actual device pin numbering and the approved fuse before connecting the branch.
Assembly drawing, p. 4, position 4
CABLE INDEX
EN / 48 OF 80
Controller to gateway Ethernet
This factory patch cable carries the cabinet’s wired data link.
MI05 / MAIN INTERIOR
Controller to gateway Ethernet
This factory patch cable carries the cabinet’s wired data link.
Inside main cabinet · data wire duct
Main controller
ETH
Cellular gateway
LAN
Factory Ethernet lead
Factory Ethernet lead
Fit the complete patch lead from ETH to LAN. Leave the molded plugs intact.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Match the ports
Identify the controller ETH port.
Identify the gateway LAN port.
2
Seat the plugs
Route the factory lead clear of AC wiring.
Seat each plug and check the retaining clip.
3
Prove the link
Check physical link indicators when fitted.
Verify the controller reaches its service.
BENCH TEST
The controller and gateway carried board telemetry. The record does not give a cable-specific link-speed test.
FIELD CHECK
Check the fitted lead and link. Keep this data lead separate from the cellular and radio antenna feeders.
Assembly drawing, p. 5. Project board communications record.
CABLE INDEX
EN / 49 OF 80
Controller to main radio RS-485
One twisted pair connects the controller to the main radio’s four-pin connector.
MI06 / MAIN INTERIOR
Controller to main radio RS-485
One twisted pair connects the controller to the main radio’s four-pin connector.
Inside main cabinet · data wire duct
Main controller
Main local radio
RS-485 A+
Four-pin plug 4 / A
A (function)
A (function)
RS-485 B−
Four-pin plug 3 / B
B (function)
B (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify
Find controller A+ and B−.
Match the radio plug view and pin numbers.
2
Trace two cores
Connect A+ to pin 4 / A.
Connect B− to pin 3 / B.
3
Prove data
Check the disconnected pair for continuity.
Check fresh position B reports across the link.
BENCH TEST
The paired radios carried position B at 9600 baud during the recorded board test.
FIELD CHECK
Verify the fitted cable, shield and serial settings. The radio hop between cabinets is wireless.
Assembly drawing, p. 5. Two-radio position return record, 11 Nov 2026.
CABLE INDEX
EN / 50 OF 80
Run and direction command pigtails
One wire per contact terminal. Keep each command pair separate on the lower strip.
MI07A / MAIN INTERIOR
Run and direction command pigtails
One wire per contact terminal. Keep each command pair separate on the lower strip.
Inside main cabinet · command wire duct
Main controller relay outputs
Lower command strip XC
CH1 COM
XC-1a,
inside
CH1 COM (function)
CH1 COM (function)
CH1 NO
XC-1b,
inside
CH1 NO (function)
CH1 NO (function)
CH2 COM
XC-2a,
inside
CH2 COM (function)
CH2 COM (function)
CH2 NO
XC-2b,
inside
CH2 NO (function)
CH2 NO (function)
CH3 COM
XC-3a,
inside
CH3 COM (function)
CH3 COM (function)
CH3 NO
XC-3b,
inside
CH3 NO (function)
CH3 NO (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Locate
Find the channel’s COM and NO at the controller.
Identify the same channel pair on the XC strip.
2
Trace one core
Run COM to the a terminal and NO to b.
Keep separate command pairs electrically apart.
3
Prove at the strip
Check continuity on the isolated pigtails.
Use the external card for the original cabinet.
BENCH TEST
The existing bench harness returned the run, forward and reverse contacts on the 13 Nov board test.
FIELD CHECK
Remove bench jumpers before field connection. Keep original interlocks and confirm field-side terminals.
Assembly drawing, pp. 2, 6. R02, XC terminal designations. Contact bench, 13 Nov 2026.
CABLE INDEX
EN / 51 OF 80
End-gun and span-spray command pigtails
One wire per contact terminal. Keep each command pair separate on the lower strip.
MI07B / MAIN INTERIOR
End-gun and span-spray command pigtails
One wire per contact terminal. Keep each command pair separate on the lower strip.
Inside main cabinet · command wire duct
Main controller relay outputs
Lower command strip XC
CH4 COM
XC-4a, inside
CH4 COM (function)
CH4 COM (function)
CH4 NO
XC-4b, inside
CH4 NO (function)
CH4 NO (function)
CH5 COM
XC-5a, inside
CH5 COM (function)
CH5 COM (function)
CH5 NO
XC-5b, inside
CH5 NO (function)
CH5 NO (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Locate
Find the channel’s COM and NO at the controller.
Identify the same channel pair on the XC strip.
2
Trace one core
Run COM to the a terminal and NO to b.
Keep separate command pairs electrically apart.
3
Prove at the strip
Check continuity on the isolated pigtails.
Use the external card for the original cabinet.
BENCH TEST
The existing harness returned the end-gun contact. The span-water circuit was left open on the 13 Nov setup.
FIELD CHECK
Remove bench jumpers before field connection. Keep original interlocks and confirm field-side terminals.
Assembly drawing, pp. 2, 6. R02, XC terminal designations. Contact bench, 13 Nov 2026.
CABLE INDEX
EN / 52 OF 80
Feedback strip to controller inputs
Seven signal pigtails follow terminal number from the feedback strip to the controller.
MI08 / MAIN INTERIOR
Feedback strip to controller inputs
Seven signal pigtails follow terminal number from the feedback strip to the controller.
Inside main cabinet · feedback wire duct
Lower feedback signals XF
Main controller digital inputs
XF-1,
inside
DI1
DI1 (function)
DI1 (function)
XF-2,
inside
DI2
DI2 (function)
DI2 (function)
XF-3,
inside
DI3
DI3 (function)
DI3 (function)
XF-4,
inside
DI4
DI4 (function)
DI4 (function)
XF-5,
inside
DI5
DI5 (function)
DI5 (function)
XF-6,
inside
DI6
DI6 (function)
DI6 (function)
XF-7,
inside
DI7
DI7 (function)
DI7 (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the signal terminals
Identify the signal side of each XF pair.
Use its matching controller DI number.
2
Trace the cores
Connect XF-n to DI-n one channel at a time.
Leave the matching R core in the return bank.
3
Prove each dry input
Test only using the approved dry input path.
Confirm the other inputs stay in their state.
BENCH TEST
The bench captured run, direction and end-gun contact inputs. DI7 was open.
FIELD CHECK
Verify installed channels and feedback meaning. Keep any original circuit voltage out of DI and DGND.
Assembly drawing, p. 7. R02, feedback terminals. Contact bench, 13 Nov 2026.
CABLE INDEX
EN / 53 OF 80
Feedback returns to block 1
Route each dry-contact return to its assigned position in the main feedback return system.
MI09A / MAIN INTERIOR
Feedback returns to block 1
Route each dry-contact return to its assigned position in the main feedback return system.
Inside main cabinet · feedback return duct
Lower feedback returns XF
Feedback return block 1
XF-1R, inside
Block 1, position 2
DI1 return (function)
DI1 return (function)
XF-2R, inside
Block 1, position 3
DI2 return (function)
DI2 return (function)
XF-3R, inside
Block 1, position 4
DI3 return (function)
DI3 return (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the matching returns
Identify the R terminal of each XF pair.
Use the correct five-position return block.
2
Route the cores
Land each return on its listed position.
Leave the signal cores on their own paths.
3
Trace to DGND
Follow the block links on MI10A and MI10B.
Check that powered feedback remains isolated.
BENCH TEST
The drawing specifies the return positions. The reference bench left DI7 open.
FIELD CHECK
Verify each return and check that no original cabinet voltage reaches the feedback input or DGND.
Assembly drawing, pp. 7–8. R02 and R03, feedback terminal names.
CABLE INDEX
EN / 54 OF 80
Feedback returns to block 2
Route each dry-contact return to its assigned position in the main feedback return system.
MI09B / MAIN INTERIOR
Feedback returns to block 2
Route each dry-contact return to its assigned position in the main feedback return system.
Inside main cabinet · feedback return duct
Lower feedback returns XF
Feedback return block 2
XF-4R, inside
Block 2,
position 2
DI4 return (function)
DI4 return (function)
XF-5R, inside
Block 2,
position 3
DI5 return (function)
DI5 return (function)
XF-6R, inside
Block 2,
position 4
DI6 return (function)
DI6 return (function)
XF-7R, inside
Block 2,
position 5
DI7 return (function)
DI7 return (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the matching returns
Identify the R terminal of each XF pair.
Use the correct five-position return block.
2
Route the cores
Land each return on its listed position.
Leave the signal cores on their own paths.
3
Trace to DGND
Follow the block links on MI10A and MI10B.
Check that powered feedback remains isolated.
BENCH TEST
The drawing specifies the return positions. The reference bench left DI7 open.
FIELD CHECK
Verify each return and check that no original cabinet voltage reaches the feedback input or DGND.
Assembly drawing, pp. 7–8. R02 and R03, feedback terminal names.
CABLE INDEX
EN / 55 OF 80
DGND to return block 1
This jumper connects the controller input common to the first feedback return block.
MI10A / MAIN INTERIOR
DGND to return block 1
This jumper connects the controller input common to the first feedback return block.
Inside main cabinet · feedback common
Main controller
Feedback return block 1
DGND
Block 1, position 1
Feedback return (function)
Feedback return (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify
Find DGND beside the controller inputs.
Find position 1 on feedback return block 1.
2
Route the jumper
Join DGND to that position.
Keep this path inside the dry feedback circuit.
3
Trace to the pair
Check isolated continuity to the return bank.
Use MI10B for the link to the second block.
BENCH TEST
The assembly drawing identifies both ends. No electrical measurement of these specific leads is recorded.
FIELD CHECK
Verify the return block as assembled. Keep original cabinet return voltage isolated from DGND.
Assembly drawing, p. 8.
CABLE INDEX
EN / 56 OF 80
Return block 1 to return block 2
The two feedback return blocks are joined by one short jumper.
MI10B / MAIN INTERIOR
Return block 1 to return block 2
The two feedback return blocks are joined by one short jumper.
Inside main cabinet · feedback common
Feedback return block 1
Feedback return block 2
Block 1, position 5
Block 2, position 1
Feedback return (function)
Feedback return (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Locate both blocks
Find position 5 on block 1.
Find position 1 on block 2.
2
Connect the link
Fit one jumper using those two positions.
Use the same feedback-return marking both ends.
3
Prove the common
Confirm continuity back to controller DGND.
Keep individual input leads out of this link.
BENCH TEST
The assembly drawing identifies both ends. No electrical measurement of these specific leads is recorded.
FIELD CHECK
Check final continuity of the two return banks to DGND and record the installed jumper.
Assembly drawing, p. 8, feedback return jumper.
CABLE INDEX
EN / 57 OF 80
Isolated run and direction feedback
The relay coil remains on the original circuit side. These pigtails leave only the dry contacts.
MI11 / MAIN INTERIOR
Isolated run and direction feedback
The relay coil remains on the original circuit side. These pigtails leave only the dry contacts.
Inside main cabinet · isolated return side
Feedback relay dry contacts
Lower feedback strip XF
K1 contact
11
XF-1, relay
side
M02-K1-11
M02-K1-11
K1 contact
14
XF-1R,
relay side
M02-K1-14
M02-K1-14
K2 contact
11
XF-2, relay
side
M03-K2-11
M03-K2-11
K2 contact
14
XF-2R,
relay side
M03-K2-14
M03-K2-14
K3 contact
11
XF-3, relay
side
M04-K3-11
M04-K3-11
K3 contact
14
XF-3R,
relay side
M04-K3-14
M04-K3-14
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the correct side
Identify the 11 and 14 dry-contact terminals.
Keep original-circuit voltage on the coil side.
2
Trace one relay
Trace 11 to the matching XF signal terminal.
Trace 14 to the matching XF return terminal.
3
Check the result
Check each dry input and its return separately.
Leave contact 12 unused on this arrangement.
BENCH TEST
The assembly and R03 show the dry-side paths. Actual fitment and separate coil-circuit tests remain site work.
FIELD CHECK
Use these labels only on the 11/14 conductors. Record the approved coil rating and field feedback source.
Assembly drawing, pp. 7–8. R03, p. 5. R02, dry-contact return map.
CABLE INDEX
EN / 58 OF 80
Isolated end-gun and panel fault feedback
The relay coil remains on the original circuit side. These pigtails leave only the dry contacts.
MI12 / MAIN INTERIOR
Isolated end-gun and panel fault feedback
The relay coil remains on the original circuit side. These pigtails leave only the dry contacts.
Inside main cabinet · isolated return side
Feedback relay dry contacts
Lower feedback strip XF
K4 contact 11
XF-4, relay side
M08-K4-11
M08-K4-11
K4 contact 14
XF-4R, relay
side
M08-K4-14
M08-K4-14
K5 contact 11
XF-5, relay side
M05-K5-11
M05-K5-11
K5 contact 14
XF-5R, relay
side
M05-K5-14
M05-K5-14
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the correct side
Identify the 11 and 14 dry-contact terminals.
Keep original-circuit voltage on the coil side.
2
Trace one relay
Trace 11 to the matching XF signal terminal.
Trace 14 to the matching XF return terminal.
3
Check the result
Check each dry input and its return separately.
Leave contact 12 unused on this arrangement.
BENCH TEST
The assembly and R03 show the dry-side paths. Actual fitment and separate coil-circuit tests remain site work.
FIELD CHECK
Use these labels only on the 11/14 conductors. Record the approved coil rating and field feedback source.
Assembly drawing, pp. 7–8. R03, p. 5. R02, dry-contact return map.
CABLE INDEX
EN / 59 OF 80
Isolated local mode and span-spray feedback
The relay coil remains on the original circuit side. These pigtails leave only the dry contacts.
MI13 / MAIN INTERIOR
Isolated local mode and span-spray feedback
The relay coil remains on the original circuit side. These pigtails leave only the dry contacts.
Inside main cabinet · isolated return side
Feedback relay dry contacts
Lower feedback strip XF
K6 contact 11
XF-6, relay side
M06-K6-11
M06-K6-11
K6 contact 14
XF-6R, relay
side
M06-K6-14
M06-K6-14
K7 contact 11
XF-7, relay side
M07-K7-11
M07-K7-11
K7 contact 14
XF-7R, relay
side
M07-K7-14
M07-K7-14
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the correct side
Identify the 11 and 14 dry-contact terminals.
Keep original-circuit voltage on the coil side.
2
Trace one relay
Trace 11 to the matching XF signal terminal.
Trace 14 to the matching XF return terminal.
3
Check the result
Check each dry input and its return separately.
Leave contact 12 unused on this arrangement.
BENCH TEST
The assembly and R03 show the dry-side paths. Actual fitment and separate coil-circuit tests remain site work.
FIELD CHECK
Use these labels only on the 11/14 conductors. Record the approved coil rating and field feedback source.
Assembly drawing, pp. 7–8. R03, p. 5. R02, dry-contact return map.
CABLE INDEX
EN / 60 OF 80
Option cabinet · isolated measurement pair
Reference low-voltage sample cabinet for cable monitoring. This is a separate optional assembly.
MI14A / MAIN INTERIOR
Option cabinet · isolated measurement pair
Reference low-voltage sample cabinet for cable monitoring. This is a separate optional assembly.
Separate optional monitor cabinet · low-voltage duct
Isolated detection board
Voltage acquisition module
Sample output, pin
TBD
VERIFY
Selected channel
AIN+
VERIFY
Sample + (function)
Sample + (function)
Same circuit
return, pin TBD
VERIFY
Same channel
AIN−
VERIFY
Sample return (function)
Sample return (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Confirm scope
Identify the optional low-voltage monitor box.
Obtain the signed detection-board drawing.
2
Trace one pair
Use the same approved acquisition channel.
Check the isolated 0–10 V signal range.
3
Keep the scope clear
Keep this pair in the low-voltage wire duct.
Use the separate approved power-circuit plan.
BENCH TEST
Reference design only. Sample pins, channels and live field detection have not been established.
FIELD CHECK
Confirm the detection-board drawing and isolation. Leave the original power-circuit landings pending.
Assembly drawing, pp. 9–10 and 17, optional monitor and separate sample-cable enclosure.
CABLE INDEX
EN / 61 OF 80
Option cabinet · acquisition module power
The optional measurement module has a separate protected DC supply branch.
MI14B / MAIN INTERIOR
Option cabinet · acquisition module power
The optional measurement module has a separate protected DC supply branch.
Separate optional monitor cabinet · low-voltage power duct
Monitor DC supply branch
Voltage acquisition module
Protected +24 V
branch
VERIFY
Module power +
+24 V (function)
+24 V (function)
Same branch 0 V
VERIFY
Module power −
0 V (function)
0 V (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the branch
Use the approved monitor-cabinet DC plan.
Confirm the branch terminals and protection.
2
Trace the two leads
Follow the protected positive feed to +.
Return through the same 0 V supply branch.
3
Prove before connecting
Confirm voltage and polarity at the module.
Test the backup supply if one is fitted.
BENCH TEST
Reference design only. The optional field module and backup runtime have not been established.
FIELD CHECK
Confirm protection, supply and backup duration on the selected monitor assembly.
Assembly drawing, pp. 9–10, optional monitor low-voltage supply.
CABLE INDEX
EN / 62 OF 80
End tower AC feed-through and earth
Three separate pigtails feed the 12 V DC supply and the protective-earth rail.
EI01 / TOWER INTERIOR
End tower AC feed-through and earth
Three separate pigtails feed the 12 V DC supply and the protective-earth rail.
Inside end tower · separated AC group
Lower AC and PE terminals
DC supply and PE rail
L feed-through,
inside
Supply AC L
L (function)
L (function)
N feed-through,
inside
Supply AC N
N (function)
N (function)
PE terminal, inside
Dedicated PE rail
PE (function)
PE (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Locate
Find L, N and PE on the lower rail.
Work with both sides isolated and verified.
2
Trace
Follow L and N to the supply input.
Follow PE to the dedicated bonding rail.
3
Prove
Check each path and the earth continuity.
Record the approved branch protection.
BENCH TEST
The assembly drawing identifies both ends. No electrical measurement of these specific leads is recorded.
FIELD CHECK
Verify the AC branch, protection and any enclosure bonding against the installed machine.
Assembly drawing, pp. 12–13.
CABLE INDEX
EN / 63 OF 80
12 V DC supply distribution
Place the positive and return leads into separate distribution blocks.
EI02 / TOWER INTERIOR
12 V DC supply distribution
Place the positive and return leads into separate distribution blocks.
Inside tower cabinet · DC duct
DC power supply
DC distribution blocks
DC +V
+12 V block,
position 1
+12 V (function)
+12 V (function)
DC −V
0 V block, position
1
0 V (function)
0 V (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify
Find +V and −V on the supply.
The block positions follow the assembly drawing.
2
Connect
Connect the positive lead to its own block.
Run the 0 V lead to the separate return block.
3
Prove
Verify polarity at the blocks before loading.
Record voltage with the fitted loads connected.
BENCH TEST
The assembly drawing identifies both ends. No electrical measurement of these specific leads is recorded.
FIELD CHECK
Verify actual wire gauge, polarity and voltage. Positive and return distribution blocks stay separate.
Assembly drawing, p. 14.
CABLE INDEX
EN / 64 OF 80
Tower local radio 12 V branch
Two separate power leads connect the device to the tower distribution blocks.
EI03A / TOWER INTERIOR
Tower local radio 12 V branch
Two separate power leads connect the device to the tower distribution blocks.
Inside tower cabinet · DC branch
12 V tower blocks
Tower local radio
+12 V block,
position 2
Four-pin plug 1 /
VCC
+12 V (function)
+12 V (function)
0 V block, position
2
Four-pin plug 2 /
GND
0 V (function)
0 V (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Locate
Locate position 2 on both tower blocks.
Use the device connector labels and orientation.
2
Connect
Keep the positive and 0 V leads together.
Land each core on its matching terminal.
3
Prove polarity
Measure at the device connector before loading.
Verify voltage again with the device powered.
BENCH TEST
The assembly drawing identifies both ends. No electrical measurement of these specific leads is recorded.
FIELD CHECK
Compare connector position with the fitted device and document the branch under load.
Assembly drawing, p. 14, position 2
CABLE INDEX
EN / 65 OF 80
GPS B receiver 12 V branch
Two separate power leads connect the device to the tower distribution blocks.
EI03B / TOWER INTERIOR
GPS B receiver 12 V branch
Two separate power leads connect the device to the tower distribution blocks.
Inside tower cabinet · DC branch
12 V tower blocks
GPS B receiver
+12 V block,
position 3
Lower row,
rightmost +
+12 V (function)
+12 V (function)
0 V block, position
3
Lower row, second
from right −
0 V (function)
0 V (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Locate
Locate position 3 on both tower blocks.
Use the device connector labels and orientation.
2
Connect
Keep the positive and 0 V leads together.
Land each core on its matching terminal.
3
Prove polarity
Measure at the device connector before loading.
Verify voltage again with the device powered.
BENCH TEST
The assembly drawing identifies both ends. No electrical measurement of these specific leads is recorded.
FIELD CHECK
Compare connector position with the fitted device and document the branch under load.
Assembly drawing, p. 14, position 3
CABLE INDEX
EN / 66 OF 80
Tower input collector 12 V branch
Two separate power leads connect the device to the tower distribution blocks.
EI03C / TOWER INTERIOR
Tower input collector 12 V branch
Two separate power leads connect the device to the tower distribution blocks.
Inside tower cabinet · DC branch
12 V tower blocks
Tower input collector
+12 V block,
position 4
Power connector +
+12 V (function)
+12 V (function)
0 V block, position
4
Power connector −
0 V (function)
0 V (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Locate
Locate position 4 on both tower blocks.
Use the device connector labels and orientation.
2
Connect
Keep the positive and 0 V leads together.
Land each core on its matching terminal.
3
Prove polarity
Measure at the device connector before loading.
Verify voltage again with the device powered.
BENCH TEST
The assembly drawing identifies both ends. No electrical measurement of these specific leads is recorded.
FIELD CHECK
Compare connector position with the fitted device and document the branch under load.
Assembly drawing, p. 14, position 4
CABLE INDEX
EN / 67 OF 80
Collector input COM positive lead
The shown input collector uses local +12 V at COM. This is separate from its power-terminal positive lead.
EI04A / TOWER INTERIOR
Collector input COM positive lead
The shown input collector uses local +12 V at COM. This is separate from its power-terminal positive lead.
Inside tower cabinet · input common
12 V tower distribution
Tower input collector
+12 V block,
position 5
Lower row COM,
left position 5
+12 V COM (function)
+12 V COM (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the poles
Locate position 5 of the positive DC block.
Find COM at position 5 from the left.
2
Fit one lead
Link the positive block to COM as shown.
Follow EI04B for the separate 0 V return.
3
Verify the circuit
Confirm this input common on the fitted unit.
Prove one isolated dry contact at a time.
BENCH TEST
This COM arrangement appears in the assembly drawing. X1 was toggled on an isolated module.
FIELD CHECK
Verify that the fitted collector requires positive COM before using the drawing.
Assembly drawing, pp. 14, 16. Isolated X1 input test, 12 Nov 2026.
CABLE INDEX
EN / 68 OF 80
0 V feed to the tower return block
The return block carries the four fault-pair returns back to the same local 0 V source.
EI04B / TOWER INTERIOR
0 V feed to the tower return block
The return block carries the four fault-pair returns back to the same local 0 V source.
Inside tower cabinet · low-voltage return
Tower 0 V distribution
Tower fault return block
0 V block, position
5
Fault return block,
position 1
0 V jumper (function)
0 V jumper (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the block positions
Find position 5 on the 0 V power block.
Find position 1 on the fault return block.
2
Trace one jumper
Connect these two 0 V positions.
Use positions 2 to 5 for the fault pairs.
3
Prove the return
Measure continuity with the system isolated.
Keep the collector COM on its +12 V lead.
BENCH TEST
The assembly drawing identifies both ends. No electrical measurement of these specific leads is recorded.
FIELD CHECK
Verify continuity to local 0 V. Keep the original powered fault circuits isolated from this return.
Assembly drawing, p. 14, negative distribution position 5 to return position 1.
CABLE INDEX
EN / 69 OF 80
RS-485 · Tower local radio
Follow this one twisted pair between the device and its assigned A and B splitter positions.
EI05A / TOWER INTERIOR
RS-485 · Tower local radio
Follow this one twisted pair between the device and its assigned A and B splitter positions.
Inside tower cabinet · data wire duct
Tower local radio
A and B splitters
Four-pin plug 4 / A
A block, position 1
A (function)
A (function)
Four-pin plug 3 / B
B block, position 1
B (function)
B (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify the pair
Find the device A and B connections.
Use position 1 on both splitters.
2
Trace and land
Trace A and B separately before connection.
Check the connector view and cable routing.
3
Prove on the bus
Check that data updates over the fitted radio.
Confirm the assigned serial settings in service.
BENCH TEST
Position B was reported over the radio. The collector kept address 2 and 9600 baud after an isolated USB power cycle.
FIELD CHECK
Verify the assembled shared radio bus with both devices reporting and each fitted tower fault cycling.
Assembly drawing, p. 15. Radio return and tower collector USB verification records.
CABLE INDEX
EN / 70 OF 80
RS-485 · GPS B receiver
Follow this one twisted pair between the device and its assigned A and B splitter positions.
EI05B / TOWER INTERIOR
RS-485 · GPS B receiver
Follow this one twisted pair between the device and its assigned A and B splitter positions.
Inside tower cabinet · data wire duct
A and B splitters
GPS B receiver
A block, position 2
Lower row,
leftmost A
A (function)
A (function)
B block, position 2
Lower row, second
from left B
B (function)
B (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify the pair
Find the device A and B connections.
Use position 2 on both splitters.
2
Trace and land
Trace A and B separately before connection.
Check the connector view and cable routing.
3
Prove on the bus
Check that data updates over the fitted radio.
Confirm the assigned serial settings in service.
BENCH TEST
Position B was reported over the radio. The collector kept address 2 and 9600 baud after an isolated USB power cycle.
FIELD CHECK
Verify the assembled shared radio bus with both devices reporting and each fitted tower fault cycling.
Assembly drawing, p. 15. Radio return and tower collector USB verification records.
CABLE INDEX
EN / 71 OF 80
RS-485 · Tower input collector
Follow this one twisted pair between the device and its assigned A and B splitter positions.
EI05C / TOWER INTERIOR
RS-485 · Tower input collector
Follow this one twisted pair between the device and its assigned A and B splitter positions.
Inside tower cabinet · data wire duct
A and B splitters
Tower input collector
A block, position 3
Lower row, left
position 6 / A/H
A (function)
A (function)
B block, position 3
Lower row, left
position 7 / B/L
B (function)
B (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Identify the pair
Find the device A and B connections.
Use position 3 on both splitters.
2
Trace and land
Trace A and B separately before connection.
Check the connector view and cable routing.
3
Prove on the bus
Check that data updates over the fitted radio.
Confirm the assigned serial settings in service.
BENCH TEST
Position B was reported over the radio. The collector kept address 2 and 9600 baud after an isolated USB power cycle.
FIELD CHECK
Verify the assembled shared radio bus with both devices reporting and each fitted tower fault cycling.
Assembly drawing, p. 15. Radio return and tower collector USB verification records.
CABLE INDEX
EN / 72 OF 80
Fault feed-through signal pigtails
Each fault signal crosses the lower rail through one dedicated feed-through terminal.
EI06A / TOWER INTERIOR
Fault feed-through signal pigtails
Each fault signal crosses the lower rail through one dedicated feed-through terminal.
Inside tower cabinet · lower fault wire duct
Tower input collector
Lower fault signals
X1, lower row
left position 4
Fault pair 1,
signal terminal
X1 (function)
X1 (function)
X2, lower row
left position 3
Fault pair 2,
signal terminal
X2 (function)
X2 (function)
X3, lower row
left position 2
Fault pair 3,
signal terminal
X3 (function)
X3 (function)
X4, lower row
left position 1
Fault pair 4,
signal terminal
X4 (function)
X4 (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Read the strip
From the left, the inputs read X4 to X1.
The lower rail pairs read X1 to X4.
2
Trace one signal
Match each X to its own fault-pair signal.
Use EI06B for the four associated returns.
3
Prove each input
Test open and closed using the dry side.
Check the App shows the recorded tower.
BENCH TEST
X1 passed on isolated USB. Address 2 and 9600 baud were checked after a separate power cycle.
FIELD CHECK
Verify X1–X4 and actual tower names on the assembled radio path. Check fresh position B during the test.
Assembly drawing, pp. 12, 16. Isolated X1 test and USB setting-retention records, 12 Nov 2026.
CABLE INDEX
EN / 73 OF 80
Fault feed-through return pigtails
Each lower rail fault pair has its own return pigtail to the local 0 V block.
EI06B / TOWER INTERIOR
Fault feed-through return pigtails
Each lower rail fault pair has its own return pigtail to the local 0 V block.
Inside tower cabinet · lower fault wire duct
Tower fault return block
Lower fault returns
Fault return
block, position
2
Fault pair 1, 0 V
terminal
X1 return (function)
X1 return (function)
Fault return
block, position
3
Fault pair 2, 0 V
terminal
X2 return (function)
X2 return (function)
Fault return
block, position
4
Fault pair 3, 0 V
terminal
X3 return (function)
X3 return (function)
Fault return
block, position
5
Fault pair 4, 0 V
terminal
X4 return (function)
X4 return (function)
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Find the matching pairs
Identify the 0 V terminal of each fault pair.
Trace its dedicated slot in the return block.
2
Trace only the return
Use positions 2 to 5 for fault pairs 1 to 4.
Position 1 receives the 0 V supply jumper.
3
Prove isolation
Check continuity to local 0 V with power off.
Verify the powered machine side is isolated.
BENCH TEST
The assembly drawing specifies all four return pigtails. The standalone X1 test did not prove the full harness.
FIELD CHECK
Verify each actual conductor and its source identification before operating the tower.
Assembly drawing, pp. 12, 14, 16. Isolated X1 input test record.
CABLE INDEX
EN / 74 OF 80
Optional tower isolation contact pigtails
Use this dry-contact routing if the isolation relays are within the end-tower assembly.
EI07 / TOWER INTERIOR
Optional tower isolation contact pigtails
Use this dry-contact routing if the isolation relays are within the end-tower assembly.
Inside tower cabinet · isolated contact side
Tower isolation relay bank
Lower fault feed-throughs
Relay
K1
contact
11
Fault
pair 1,
signal
terminal
E02-K1-11
E02-K1-11
Relay
K1
contact
14
Fault
pair 1, 0
V return
E02-K1-14
E02-K1-14
Relay
K2
contact
11
Fault
pair 2,
signal
terminal
E02-K2-11
E02-K2-11
Relay
K2
contact
14
Fault
pair 2, 0
V return
E02-K2-14
E02-K2-14
Relay
K3
contact
11
Fault
pair 3,
signal
terminal
E02-K3-11
E02-K3-11
Relay
K3
contact
14
Fault
pair 3, 0
V return
E02-K3-14
E02-K3-14
Relay
K4
contact
11
Fault
pair 4,
signal
terminal
E02-K4-11
E02-K4-11
Relay
K4
contact
14
Fault
pair 4, 0
V return
E02-K4-14
E02-K4-14
Terminals are arranged for tracing. Follow the markings on the fitted components.
Solid line · documented wiring route
Dashed line + open end · confirm on site
Colors distinguish routes. Use the printed core IDs.
1
Locate the relay bank
Confirm where the relays are actually mounted.
Use E02 for an external isolation enclosure.
2
Trace the dry side
Route each 11 to its paired fault signal.
Route each 14 to that pair’s local 0 V.
3
Verify the separation
Keep the powered circuit on A1/A2.
Check the four dry paths after assembly.
BENCH TEST
R03 defines the dry-side tags. The standalone X1 check did not verify the optional relay paths.
FIELD CHECK
Confirm approved relay placement, input mapping and the function of each original-machine circuit.
R03, p. 5, E02 dry contacts. Assembly drawing, pp. 14, 16.
CABLE INDEX
EN / 75 OF 80
Commission travel, stop and local control
Record the request, the independent feedback and what the installer actually observed.
COM-1 / COMMISSIONING & RECORDS
Commission travel, stop and local control
Record the request, the independent feedback and what the installer actually observed.
1
Check original controls
With the approved test method, prove local start, local stop, emergency
stop, limits and forward/reverse interlocks. Record the local selector position
and independent mode indication.
2
Prove inputs before motion
Use an isolated fixture or approved test contact. Change one input at a time,
check its expected return and show it releases. Remove temporary jumpers
and restore the field routing.
3
Witness forward travel
Select the identified machine. Request forward and start. Observe actual
movement, DI1 run and DI2 forward together. Check reverse indication
remains inactive. Record time and direction.
4
Stop and confirm standstill
Issue stop. Record output release, returned run and direction inputs,
physical standstill and stopping distance or angle. Confirm the site is clear
before requesting the opposite direction.
5
Witness reverse travel
Request reverse then start under the approved trial. Verify physical
direction, DI1 run and DI3 reverse. Stop and confirm both feedbacks
release. Exercise local takeover per the signed plan.
6
Record loss and recovery
Use the approved plan for missing feedback, contradictory inputs or loss of
communications. Record the fault, local authority and recovery. Verify the
machine stays in the expected state after reconnection.
Main cable schedule R02, factory and field tests / Board and jumper-harness acceptance, 13 Nov 2026
CABLE INDEX
EN / 76 OF 80
Commission water, data and fitted options
Perform each test against the installed device and its assigned channel.
COM-2 / COMMISSIONING & RECORDS
Commission water, data and fitted options
Perform each test against the installed device and its assigned channel.
1
Span water and end gun
Operate each fitted circuit separately. Read its independent return and
observe the actual valve, pump or spray. Check the shutdown state. Record
where the indication comes from.
2
Tower faults
Trigger each approved test point separately, then reset it. Match the physical
tower to the correct X input and App record. Check that other inputs hold
their state and position B remains fresh.
3
Cellular link and radio
Record the fitted gateway, local carrier, working network and antenna ports.
Verify the center-to-tower radio separately. Interrupt and restore each link
using the approved test plan.
4
Center and tower position
Check the fixed center and a fresh tower fix with timestamps. During a tower
interruption, verify that the previous B position is shown as last known. Verify
recovery on fresh data.
5
Speed and sensors
For an assigned speed output, verify timing and actual travel. For each fitted
sensor verify supply, connector, bus address, scaling, timestamps and the
observed reading. Protect unused cores.
6
Cable monitor
Compare the protected conductor, power state, telemetry and notification.
Witness the approved loss-of-power and conductor-fault tests separately.
Record backup runtime when fitted.
Cable schedule R02 / Assembly drawings, pp. 9–17 / Cable label schedule R03
CABLE INDEX
EN / 77 OF 80
As-built cable and core record
Print a copy for each physical cable segment. Enter the terminal actually used at each end.
RECORD / COMMISSIONING & RECORDS
As-built cable and core record
Print a copy for each physical cable segment. Enter the terminal actually used at each end.
Site / machine
Cable / segment / length
Drawing / revision
Core ID
End A · location / terminal
End B · location / terminal
Test / result
Date / initials
Cable type / circuit voltage / bonding arrangement
Open conductors, individually insulated spares or additional witness notes
Site record / Attach traced drawing, measured values and installation photos.
CABLE INDEX
EN / 78 OF 80
Acceptance and handover
Complete this page with the electrician, site witness and owner.
HANDOVER / COMMISSIONING & RECORDS
Acceptance and handover
Complete this page with the electrician, site witness and owner.
Electrical installation
Attach the signed drawings, cable lengths, landed terminals, protective
bonding and enclosure checks. Record which conductors or options
remain parked.
Observed operation
Attach the travel, stop, local takeover and fault records. Include water,
tower or option evidence only for the installed configuration.
Operator handover
Identify the machine in the App. Show normal stop, local control, stale
position and returned feedback. Record who witnessed each action.
Open items
Identify the specific circuit, unconfirmed endpoint, responsible person and
test still due. Attach the updated as-built record before releasing that
function.
Electrical installer
Signature / date
Site witness
Signature / date
Owner / operator
Signature / date
Use with the machine-specific terminal schedule and commissioning records.
CABLE INDEX
EN / 79 OF 80
What the project records establish
Use the circuit-specific bench and field notes at the foot of every wiring sheet.
EVIDENCE / COMMISSIONING & RECORDS
What the project records establish
Use the circuit-specific bench and field notes at the foot of every wiring sheet.
1
Cabinet assembly drawings
The 17-page assembly guide identifies the two enclosures, internal supply
distribution, command and input rails, data cables, roof feeders and the
separate prototype cable-monitor components.
2
R02 terminal schedule
The main cabinet core schedule and its test sheet identify controller and rail
designations. Original cabinet references lead the electrician to a circuit to
trace. Final field landings require the site drawing.
3
R03 jacket and core labels
The five-page cable guide and print schedule cover the eleven main outlets,
two tower outlets, five antenna feeders, optional spares and the
machine-side and controller-side relay cable variants.
4
Control board and contact harness
On 13 Nov 2026 the existing harness returned run, forward, reverse and
end-gun inputs. Final stop cleared the observed inputs and outputs. Verify
the field motor, new wiring and water circuits separately.
5
Tower and positioning tests
The isolated tower module registered X1 changing state on 12 Nov. Address
2 at 9600 baud was separately read back after a power cycle. Confirm all
four installed tower alarms over radio and fresh position B.
6
Optional timer and cable monitor
The standard timer sequence has a recorded software case. Its physical
output and the original timer changeover await approval. Original
conductors, residual-voltage checks and any monitor backup supply require
site evidence.
Assembly drawing / Original machine schematics / R02 and R03 / Nov 2026 project test records
CABLE INDEX
EN / 80 OF 80