technical article

For a rooftop PV bid that combines east- and west-facing…

November 22, 2026Updated: November 22, 20265 min readFact Checked
Cinn Song

Cinn Song

Founder & Chief Solutions Architect

For a rooftop PV bid that combines east- and west-facing…

TL;DR

Require explicit east and west modeling before accepting a rooftop PV yield estimate. Screen with two PVWatts V8 runs using each plane’s DC capacity, tilt, azimuth and losses and the same site weather file. Verify the proposed inverter arrangement before relying on a shared-inverter AC total.

Require explicit east and west modeling when evaluating a rooftop PV bid. Use two PVWatts V8 screening runs with plane-specific capacity, geometry and losses and a common site weather file. For a shared inverter, require a combined AC estimate that represents the proposed equipment layout.

Summary

Require explicit east and west modeling when evaluating a rooftop PV bid. Use two PVWatts V8 screening runs with plane-specific capacity, geometry and losses and a common site weather file. For a shared inverter, require a combined AC estimate that represents the proposed equipment layout.

Key Takeaways

  • Ask the bidder to show the modeled east and west tilt and azimuth against the roof drawing.
  • Reconcile the DC capacity assigned to both planes with the quoted project capacity.
  • Check the weather source and filename returned for each PVWatts V8 run.
  • Request the mounting, loss, DC-to-AC ratio and inverter efficiency assumptions used in each run.
  • Use monthly and annual AC energy for yield review. Request hourly AC output when evaluating generation timing.
  • Verify the combined AC estimate against the proposed inverter layout, especially when the roof planes share an inverter.

Require separate east and west inputs in rooftop PV bids

Require the bidder to model each roof orientation explicitly before using the yield estimate to select a bid. Request the installed DC capacity, tilt, azimuth, mounting type, and loss assumptions for each plane, plus the site weather file and proposed inverter layout. Two PVWatts V8 runs are a practical screening method. When both planes feed a shared inverter, ask for a system model that represents that arrangement before relying on the combined AC estimate. PVWatts V8 API · SAM Module help

1. Check which roof planes the estimate represents

For a rooftop PV bid that combines east- and west-facing… — Detailed functional anatomy

A PVWatts V8 API request takes one tilt, one azimuth, and one nameplate capacity. If a bidder enters the full project capacity with an averaged azimuth, the result represents the single geometry entered. Ask for the roof layout and the model inputs side by side. Match the east and west azimuths and tilts to the drawing, then reconcile the capacities assigned to each plane with the total in the bid. Apply this check even if both planes have the same tilt or module count. PVWatts V8 API, Request Parameters

2. Ask for two reproducible screening runs

For a rooftop PV bid that combines east- and west-facing… — Detailed system operations and maintenance

Ask the bidder to use each plane’s own geometry and DC capacity, with a common weather resource for both runs at the same site. PVWatts V8 accepts site coordinates or a climate file identifier. Request the returned station_info so you can compare the weather source and resource filename in both runs. Also ask the bidder to identify any inputs left at defaults, including the DC-to-AC ratio and rated inverter efficiency, and explain how any plane-specific losses were assigned. Keep those assumptions with the bid so a revised layout can be checked against the original estimate. PVWatts V8 API, Request Parameters and Station Info Fields

3. Compare output at the resolution the decision needs

Request monthly and annual AC energy for each plane. PVWatts V8 reports these as ac_monthly and ac_annual in kWh AC. When the bid depends on when the building can use the generation, request the hourly ac series, which the API reports in watts AC, and ask the bidder to document how its time basis aligns with the building’s load records. Review the orientation-level results alongside the site total so you can trace a revised estimate back to the roof plane and assumptions that changed. PVWatts V8 API, Station Info Fields and Output Fields

4. Verify the combined AC estimate against the inverter layout

The PVWatts V8 API documents a DC-to-AC ratio and rated inverter efficiency for each run. For a shared-inverter bid, ask the bidder to show how both orientations feed the proposed inverter configuration and how that configuration is represented in the combined AC result. Treat separately modeled AC totals as a screening estimate while the shared configuration is unverified. SAM’s Module help describes a detailed PV configuration with identical modules arranged in up to four DC subarrays and feeding one or more inverters. If the bidder uses that configuration, request the model file, the east and west subarray settings, and the inverter assumptions. Compare them with the quoted equipment schedule and electrical drawing before accepting the estimate. PVWatts V8 API, Request Parameters · SAM Module help

FAQ

Is an averaged azimuth sufficient for bid evaluation?

Ask for both actual azimuths. A PVWatts V8 request accepts one azimuth, so an average represents a single input geometry. PVWatts V8 API

Does equal tilt justify one PVWatts run?

Model both planes even if their tilts match. PVWatts V8 takes tilt and azimuth as separate inputs. PVWatts V8 API

Can I accept one report covering the whole roof?

Yes, if it shows both orientations explicitly and documents how the combined AC result represents the proposed inverter layout. SAM Module help

What records make the PVWatts runs reviewable?

Ask for the model version, non-credential inputs, weather information, output files, and any warnings. PVWatts V8 returns version, weather, and warning fields. PVWatts V8 API

Which output should I use for annual generation?

Use ac_annual for modeled annual AC energy in kWh. Use ac_monthly to review the monthly energy profile. PVWatts V8 API

When should I request hourly output?

Ask for it when generation timing matters to the purchase decision. Request timeframe=hourly and check the time basis before comparing the AC power series with site load records. PVWatts V8 API

Can I use two PVWatts AC results for a shared inverter?

Use them for screening. Before accepting the site AC estimate, ask for a model that shows how both orientations feed the quoted inverter configuration. PVWatts V8 API · SAM Module help

What if the bidder uses the detailed SAM PV model?

Request the case file and check the module selection, east and west subarray settings, and inverter configuration against the bid. SAM’s Module help describes the subarray configuration for identical modules. SAM Module help

About the Author

Cinn Song

Cinn Song

Founder & Chief Solutions Architect

Cinn Song founded SOLARTODO LIMITED and leads its smart-city infrastructure engineering — from solar, storage and integrated smart poles to the company's push into physical-AI city edge nodes: pole-mounted edge computing, vertical LLMs for smart cities, drone-based O&M with autonomous battery swapping, robotic maintenance, and high-speed counter-UAS interception. Since 2010, he has directed turnkey EPC + BOT delivery across 50+ countries, including telecom monopole supply for national grid operators, off-grid solar street-lighting for African municipalities, and integrated smart-pole programs for Gulf smart cities.

View All Posts

Cite This Article

APA

Cinn Song. (2026). For a rooftop PV bid that combines east- and west-facing…. SOLARTODO. Retrieved from https://solartodo.com/knowledge/for-a-rooftop-pv-bid-that-combines-east-and-west-facing-roof-planes-should-the-buyer-accept-a-single-pvwatts-run

BibTeX
@article{solartodo_for_a_rooftop_pv_bid_that_combines_east_and_west_facing_roof_planes_should_the_buyer_accept_a_single_pvwatts_run,
  title = {For a rooftop PV bid that combines east- and west-facing…},
  author = {Cinn Song},
  journal = {SOLARTODO Knowledge Base},
  year = {2026},
  url = {https://solartodo.com/knowledge/for-a-rooftop-pv-bid-that-combines-east-and-west-facing-roof-planes-should-the-buyer-accept-a-single-pvwatts-run},
  note = {Accessed: 2026-11-22}
}

Published: November 22, 2026 | Available at: https://solartodo.com/knowledge/for-a-rooftop-pv-bid-that-combines-east-and-west-facing-roof-planes-should-the-buyer-accept-a-single-pvwatts-run